Energy Projects Near You

Solar, wind and battery projects near Bath (BA1)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BA1 (Bath and North East Somerset): 5 approved but not yet running, 2 operational. The largest live scheme is Royal United Hospital, Combe Park (0.3 MW rooftop solar, approved on 25 April 2025, not yet built), 2.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
0awaiting a decision
5approved, not running
2operational

Projects within 10 km of BA1

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ashley Garagesolar farmsolar farm1.1application withdrawnupdated Feb 2024Sep 2023—Feb 2024Wiltshire7.5
Gypsy Lane, Burnett Solar PV Arrayssolar farmsolar farm24.5refusedupdated Jan 2026Jul 2024refused Sep 2025Jan 2026Bath and North East Somerset8.6
Kingston Farmsolar farmsolar farm5operationalupdated Mar 2013Mar 2011granted May 2011Mar 2013Wiltshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
LiveWest Homesrooftop solarrooftop solar—refusedupdated Jun 2026Mar 2026refused May 2026Jun 2026Bath and North East Somerset1.2
Bath Sports And Leisure Centre, North Parade Roadrooftop solarrooftop solar—under constructionupdated Feb 2025Aug 2024granted Oct 2024Feb 2025Bath and North East Somerset1.4
King Edwards School, North Roadrooftop solarrooftop solar0.2under constructionupdated May 2023Apr 2023—May 2023Bath and North East Somerset1.4
Royal United Hospital, Combe Parkrooftop solarrooftop solar0.3approved, not builtupdated Jun 2025Mar 2025granted Apr 2025Jun 2025Bath and North East Somerset2.1
Ashley Garagebattery storagebattery storage0.5application withdrawnupdated Feb 2024Sep 2023—Feb 2024Wiltshire7.5
St Laurence School, Ashley Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Wiltshire8.4
Wellsway School, Chandag Road PV Arraysrooftop solarrooftop solar0.1approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024Bath and North East Somerset8.9
Hare Breweryrooftop solarrooftop solar0.2operationalupdated Feb 2024Jul 2019granted Aug 2019Feb 2024South Gloucestershire9.5

Distance from the average position of the BA1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300110
Rooftop solar705110.9
Battery storage100000

MW in pipeline: pending, approved and under-construction capacity.

How Bath and North East Somerset decides solar, wind and battery applications

ApplicationsBath and North East SomersetUK
Decided applications (solar, wind, battery)1910,236
Refused5 (26%)19%
Solar refused5 of 1712%
Battery storage refused0 of 216%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Bath and North East Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.