Solar, wind and battery projects near Bath (BA2)
17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BA2 (Bath and North East Somerset): 10 approved but not yet running, 3 operational. The largest live scheme is Marksbury Plain Solar Park (15 MW solar farm, approved on 1 July 2022, not yet built; REPD status may be out of date), 8.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BA2
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Marksbury Plain Solar Parksolar farm | solar farm | 15 | approved, not built may be out of dateupdated Mar 2025 | Jan 2022 | granted Jul 2022 | Mar 2025 | Bath and North East Somerset | 8.0 |
| Gypsy Lane, Burnett Solar PV Arrayssolar farm | solar farm | 24.5 | refusedupdated Jan 2026 | Jul 2024 | refused Sep 2025 | Jan 2026 | Bath and North East Somerset | 8.1 |
| Wilmington Farmsolar farm | solar farm | 7.6 | refusedupdated Apr 2013 | Oct 2012 | refused Feb 2013 | Apr 2013 | Bath and North East Somerset | 8.6 |
| Hunstrete (Wilmington Farm)solar farm | solar farm | 2.3 | operationalupdated Feb 2016 | Feb 2014 | granted Jun 2014 | Feb 2016 | Bath and North East Somerset | 8.7 |
| Fairy Hill, Compton Dando Solar Farmsolar farm | solar farm | 2.1 | approved, not builtupdated Dec 2025 | Dec 2023 | granted Jul 2025 | Dec 2025 | Bath and North East Somerset | 9.3 |
| Kingston Farmsolar farm | solar farm | 5 | operationalupdated Mar 2013 | Mar 2011 | granted May 2011 | Mar 2013 | Wiltshire | 9.5 |
| Chelwood Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2016 | May 2014 | granted Sep 2014 | Jul 2016 | Bath and North East Somerset | 9.5 |
| Midsomer Nortonbattery storage | battery storage | 6 | under constructionupdated Aug 2022 | Jul 2021 | granted Dec 2022 | Aug 2022 | Bath and North East Somerset | 9.8 |
| The Flattssolar | solar | 6.8 | refusedupdated Aug 2014 | Mar 2014 | refused Jun 2014 | Aug 2014 | Bath and North East Somerset | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| LiveWest Homesrooftop solar | rooftop solar | — | refusedupdated Jun 2026 | Mar 2026 | refused May 2026 | Jun 2026 | Bath and North East Somerset | 2.8 |
| Bath Sports And Leisure Centre, North Parade Roadrooftop solar | rooftop solar | — | under constructionupdated Feb 2025 | Aug 2024 | granted Oct 2024 | Feb 2025 | Bath and North East Somerset | 3.1 |
| Royal United Hospital, Combe Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2025 | Mar 2025 | granted Apr 2025 | Jun 2025 | Bath and North East Somerset | 3.7 |
| King Edwards School, North Roadrooftop solar | rooftop solar | 0.2 | under constructionupdated May 2023 | Apr 2023 | — | May 2023 | Bath and North East Somerset | 3.9 |
| Optima Products, Mill Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | Bath and North East Somerset | 8.3 |
| St Laurence School, Ashley Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Wiltshire | 8.4 |
| Stowford Manor Farm, Farleigh Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Apr 2023 | granted Jul 2023 | Jul 2023 | Wiltshire | 8.7 |
| Wellsway School, Chandag Road PV Arraysrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Oct 2024 | Jul 2024 | granted Sep 2024 | Oct 2024 | Bath and North East Somerset | 9.4 |
Distance from the average position of the BA2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 2 | 3 | 2 | 17.1 |
| Rooftop solar | 8 | 0 | 7 | 0 | 1 | 1.3 |
| Solar | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 1 | 0 | 1 | 0 | 0 | 6 |
MW in pipeline: pending, approved and under-construction capacity.
How Bath and North East Somerset decides solar, wind and battery applications
| Applications | Bath and North East Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 5 (26%) | 19% |
| Solar refused | 5 of 17 | 12% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 17.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
All projects in Bath and North East Somerset
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BA2, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.