Solar, wind and battery projects near Bristol (BS31)
37 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS31 (Bath and North East Somerset): 6 are waiting for a planning decision, 22 approved but not yet running, 4 operational. The largest live scheme is Stowey Road, Stowey Solar Farm (49.9 MW solar farm, approved on 24 July 2025, not yet built), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BS31
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Gypsy Lane, Burnett Solar PV Arrayssolar farm | solar farm | 24.5 | refusedupdated Jan 2026 | Jul 2024 | refused Sep 2025 | Jan 2026 | Bath and North East Somerset | 2.0 |
| Fairy Hill, Compton Dando Solar Farmsolar farm | solar farm | 2.1 | approved, not builtupdated Dec 2025 | Dec 2023 | granted Jul 2025 | Dec 2025 | Bath and North East Somerset | 3.2 |
| Wilmington Farmsolar farm | solar farm | 7.6 | refusedupdated Apr 2013 | Oct 2012 | refused Feb 2013 | Apr 2013 | Bath and North East Somerset | 6.3 |
| Hunstrete (Wilmington Farm)solar farm | solar farm | 2.3 | operationalupdated Feb 2016 | Feb 2014 | granted Jun 2014 | Feb 2016 | Bath and North East Somerset | 6.4 |
| Marksbury Plain Solar Parksolar farm | solar farm | 15 | approved, not built may be out of dateupdated Mar 2025 | Jan 2022 | granted Jul 2022 | Mar 2025 | Bath and North East Somerset | 6.5 |
| Feeder Roadbattery storage | battery storage | 20 | operationalupdated Jan 2024 | Oct 2019 | granted Mar 2020 | Jan 2024 | Bristol | 6.6 |
| Partfield Farmwind farm | wind farm | 5.6 | application withdrawnupdated Feb 2004 | Oct 2000 | — | Feb 2004 | South Gloucestershire | 6.8 |
| Philip Street Car Breakersbattery storage | battery storage | 7.2 | approved, not built may be out of dateupdated Jun 2023 | May 2020 | granted Jun 2020 | Jun 2023 | Bristol | 6.8 |
| Chelwood Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2016 | May 2014 | granted Sep 2014 | Jul 2016 | Bath and North East Somerset | 6.9 |
| East Dundry Lane, Norton Hawkfieldsolar farm | solar farm | 15 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Bath and North East Somerset | 7.2 |
| East Dundry Lane, Norton Hawkfield Solar Farmsolar farm | solar farm | 15 | application submittedupdated Dec 2025 | Jul 2025 | — | Dec 2025 | North Somerset | 8.4 |
| The Flattssolar | solar | 6.8 | refusedupdated Aug 2014 | Mar 2014 | refused Jun 2014 | Aug 2014 | Bath and North East Somerset | 8.5 |
| Stowey Road, Stowey Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Nov 2024 | granted Jul 2025 | Feb 2026 | Bath and North East Somerset | 9.6 |
| Hersey Gardenssolar farm | solar farm | 2 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | Bristol | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wellsway School, Chandag Road PV Arraysrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Oct 2024 | Jul 2024 | granted Sep 2024 | Oct 2024 | Bath and North East Somerset | 0.3 |
| Gallagher Retail Park, Aldermoor Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | South Gloucestershire | 4.2 |
| Robinson House Nursing Home, Sturminster Road Solar Photovoltaicsrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Bristol | 4.3 |
| Hollywood Bowl, Aspects Leisure Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 | South Gloucestershire | 4.6 |
| Longwell Green Leisure Centrerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Aug 2024 | May 2024 | granted Jul 2024 | Aug 2024 | South Gloucestershire | 4.6 |
| Hare Breweryrooftop solar | rooftop solar | 0.2 | operationalupdated Feb 2024 | Jul 2019 | granted Aug 2019 | Feb 2024 | South Gloucestershire | 4.9 |
| Warmley Park School, Tower Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | South Gloucestershire | 5.4 |
| Sainsburys Superstore, Regent Streetrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — | South Gloucestershire | 6.1 |
| Avon Meads, Hollywood Bowlrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Bristol | 6.4 |
| Hill Farm, East Dundry Road Solar Farmsolar farm | solar farm | — | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | Bristol | 6.4 |
| Western Drive, Hengroverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Bristol | 6.5 |
| Bottle Yard Studios (TBY2)rooftop solar | rooftop solar | 1 | approved, not builtupdated Apr 2022 | Mar 2022 | granted Jun 2022 | Apr 2022 | Bristol | 7.0 |
| Royal United Hospital, Combe Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2025 | Mar 2025 | granted Apr 2025 | Jun 2025 | Bath and North East Somerset | 7.3 |
| Drive Vauxhall, Avon Streetbattery storage | battery storage | 0.6 | approved, not builtupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 | Bristol | 7.4 |
| Peterson Avenue, Hartcliffe Solar Photovoltaics PV equipmentrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Mar 2022 | Dec 2021 | Bristol | 7.5 |
| Cotswold House, St Philips Road - olar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | Nov 2023 | granted Jun 2024 | Jul 2024 | Bristol | 7.8 |
| Queens Road, Bishopsworthrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Bristol | 8.7 |
| East Dundry Lane, Norton Hawsfield Solar Farmsolar farm | solar farm | — | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | North Somerset | 8.8 |
| Canons Way, City Centre Solar Photovoltaics Equipmentrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | Bristol | 8.9 |
| LiveWest Homesrooftop solar | rooftop solar | — | refusedupdated Jun 2026 | Mar 2026 | refused May 2026 | Jun 2026 | Bath and North East Somerset | 9.0 |
| Sainsburys Supermarkets Limited, The Villagerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | South Gloucestershire | 9.4 |
| David Lloyd Leisure Club, Willowherb Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | South Gloucestershire | 9.6 |
| Iaaps, Newlands Lane Solar Panels & Hydrogen Storagerooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Nov 2022 | Sep 2022 | granted Oct 2022 | Nov 2022 | South Gloucestershire | 9.8 |
Distance from the average position of the BS31 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 5 | 3 | 2 | 2 | 99 |
| Rooftop solar | 20 | 1 | 17 | 1 | 1 | 5.2 |
| Solar | 1 | 0 | 0 | 0 | 1 | 0 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 3 | 0 | 2 | 1 | 0 | 7.8 |
MW in pipeline: pending, approved and under-construction capacity.
How Bath and North East Somerset decides solar, wind and battery applications
| Applications | Bath and North East Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 5 (26%) | 19% |
| Solar refused | 5 of 17 | 12% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 17.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
All projects in Bath and North East Somerset
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS31, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.