Solar, wind and battery projects near Bristol (BS14)
42 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS14 (Bristol): 6 are waiting for a planning decision, 26 approved but not yet running, 6 operational. The largest live scheme is Stowey Road, Stowey Solar Farm (49.9 MW solar farm, approved on 24 July 2025, not yet built), 8.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BS14
Projects of 1 MW and more (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| East Dundry Lane, Norton Hawkfieldsolar farm | solar farm | 15 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Bath and North East Somerset | 3.8 |
| Feeder Roadbattery storage | battery storage | 20 | operationalupdated Jan 2024 | Oct 2019 | granted Mar 2020 | Jan 2024 | Bristol | 3.8 |
| East Dundry Lane, Norton Hawkfield Solar Farmsolar farm | solar farm | 15 | application submittedupdated Dec 2025 | Jul 2025 | — | Dec 2025 | North Somerset | 3.9 |
| Philip Street Car Breakersbattery storage | battery storage | 7.2 | approved, not built may be out of dateupdated Jun 2023 | May 2020 | granted Jun 2020 | Jun 2023 | Bristol | 3.9 |
| Hersey Gardenssolar farm | solar farm | 2 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | Bristol | 4.8 |
| Fairy Hill, Compton Dando Solar Farmsolar farm | solar farm | 2.1 | approved, not builtupdated Dec 2025 | Dec 2023 | granted Jul 2025 | Dec 2025 | Bath and North East Somerset | 5.2 |
| Gypsy Lane, Burnett Solar PV Arrayssolar farm | solar farm | 24.5 | refusedupdated Jan 2026 | Jul 2024 | refused Sep 2025 | Jan 2026 | Bath and North East Somerset | 6.0 |
| Epic Long Ashton, Phase 1 - 3 Office Buildingssolar farm | solar farm | 1.1 | under constructionupdated Mar 2026 | Oct 2023 | granted Mar 2025 | Mar 2026 | North Somerset | 6.2 |
| Partfield Farmwind farm | wind farm | 5.6 | application withdrawnupdated Feb 2004 | Oct 2000 | — | Feb 2004 | South Gloucestershire | 7.6 |
| Chelwood Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2016 | May 2014 | granted Sep 2014 | Jul 2016 | Bath and North East Somerset | 7.9 |
| Wilmington Farmsolar farm | solar farm | 7.6 | refusedupdated Apr 2013 | Oct 2012 | refused Feb 2013 | Apr 2013 | Bath and North East Somerset | 7.9 |
| Hunstrete (Wilmington Farm)solar farm | solar farm | 2.3 | operationalupdated Feb 2016 | Feb 2014 | granted Jun 2014 | Feb 2016 | Bath and North East Somerset | 8.0 |
| Stowey Road, Stowey Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Nov 2024 | granted Jul 2025 | Feb 2026 | Bath and North East Somerset | 8.0 |
| Lockleaze Energy Storagebattery storage | battery storage | 15 | operationalupdated Jan 2019 | Mar 2017 | — | Jan 2019 | Bristol | 8.0 |
| Marksbury Plain Solar Parksolar farm | solar farm | 15 | approved, not built may be out of dateupdated Mar 2025 | Jan 2022 | granted Jul 2022 | Mar 2025 | Bath and North East Somerset | 8.5 |
| The Flattssolar | solar | 6.8 | refusedupdated Aug 2014 | Mar 2014 | refused Jun 2014 | Aug 2014 | Bath and North East Somerset | 9.4 |
| Haberfield Park Farm Solar Farmsolar farm | solar farm | 5 | approved, not builtupdated Nov 2023 | May 2023 | granted Nov 2023 | Nov 2023 | North Somerset | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Robinson House Nursing Home, Sturminster Road Solar Photovoltaicsrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Bristol | 0.7 |
| Western Drive, Hengroverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Bristol | 1.6 |
| Hill Farm, East Dundry Road Solar Farmsolar farm | solar farm | — | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | Bristol | 1.8 |
| Bottle Yard Studios (TBY2)rooftop solar | rooftop solar | 1 | approved, not builtupdated Apr 2022 | Mar 2022 | granted Jun 2022 | Apr 2022 | Bristol | 2.0 |
| Peterson Avenue, Hartcliffe Solar Photovoltaics PV equipmentrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Mar 2022 | Dec 2021 | Bristol | 2.7 |
| Queens Road, Bishopsworthrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Bristol | 3.8 |
| Avon Meads, Hollywood Bowlrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Bristol | 3.9 |
| East Dundry Lane, Norton Hawsfield Solar Farmsolar farm | solar farm | — | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | North Somerset | 4.2 |
| Drive Vauxhall, Avon Streetbattery storage | battery storage | 0.6 | approved, not builtupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 | Bristol | 4.3 |
| Cotswold House, St Philips Road - olar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | Nov 2023 | granted Jun 2024 | Jul 2024 | Bristol | 4.8 |
| Canons Way, City Centre Solar Photovoltaics Equipmentrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | Bristol | 4.8 |
| Wellsway School, Chandag Road PV Arraysrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Oct 2024 | Jul 2024 | granted Sep 2024 | Oct 2024 | Bath and North East Somerset | 5.3 |
| Great Western Air Ambulance Charityrooftop solar | rooftop solar | 0.2 | operationalupdated Aug 2024 | — | — | Aug 2024 | Bristol | 5.4 |
| David Lloyd Leisure Plc, Ashton Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Sep 2023 | Oct 2023 | Bristol | 5.4 |
| Gallagher Retail Park, Aldermoor Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | South Gloucestershire | 5.9 |
| Hollywood Bowl, Aspects Leisure Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 | South Gloucestershire | 6.1 |
| Longwell Green Leisure Centrerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Aug 2024 | May 2024 | granted Jul 2024 | Aug 2024 | South Gloucestershire | 6.1 |
| All Saints Church, Pembroke Road - Photovoltaic Panelsrooftop solar | rooftop solar | — | approved, not builtupdated May 2026 | Nov 2022 | granted May 2024 | May 2026 | Bristol | 6.6 |
| Sainsburys Superstore, Regent Streetrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — | South Gloucestershire | 6.7 |
| Warmley Park School, Tower Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | South Gloucestershire | 7.6 |
| Hare Breweryrooftop solar | rooftop solar | 0.2 | operationalupdated Feb 2024 | Jul 2019 | granted Aug 2019 | Feb 2024 | South Gloucestershire | 8.0 |
| Lockleaze Sports Centre, Bonnington Walkbattery storage | battery storage | 0.2 | approved, not builtupdated Oct 2023 | Feb 2023 | granted Oct 2023 | Oct 2023 | Bristol | 9.1 |
| Bonnington Walk, Lockleaze - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Bristol | 9.1 |
| Lockleaze Sports Centre, Bonnington Walk - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Bristol | 9.1 |
| University Of West Of England, Coldharbour Lanerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Sep 2024 | Sep 2024 | South Gloucestershire | 9.9 |
Distance from the average position of the BS14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 14 | 5 | 5 | 2 | 2 | 105 |
| Rooftop solar | 19 | 1 | 16 | 2 | 0 | 4.7 |
| Solar | 1 | 0 | 0 | 0 | 1 | 0 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 7 | 0 | 5 | 2 | 0 | 8.4 |
MW in pipeline: pending, approved and under-construction capacity.
How Bristol decides solar, wind and battery applications
| Applications | Bristol | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 32 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 18 | 12% |
| Onshore wind refused | 0 of 6 | 45% |
| Battery storage refused | 0 of 8 | 16% |
| Median time from submission to decision | 14.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS14, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.