East Dundry Lane, Norton Hawkfield Solar Farm (15 MW)

East Dundry Lane, Norton Hawkfield Solar Farm is a 15 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 2 July 2025, no decision recorded; the record was last updated on 2 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
application submittedstatus in REPD
2 December 2025record last updated
North Somersetcouncil area

Planning timeline

DateStage
2 July 2025Application submitted

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
application submitted
Record last updated
2 December 2025
Operator or applicant
Enviromena
Planning authority
North Somerset
Planning application reference
25/02595/EFUL
Site area
16.6 ha
Address (REPD)
Parcel 3470, East Dundry Lane, Norton Hawkfield, Bristol
Council area (by location)
North Somerset
Name in REPD
East Dundry Lane, Norton Hawkfield - Solar Farm
REPD reference
19279

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Dundry Lane, Norton Hawkfieldsolar farm15application submitted2.1
Stowey Road, Stowey Solar Farmsolar farm49.9approved, not built6.1
Philip Street Car Breakersbattery storage7.2approved, not built6.8
Feeder Roadbattery storage20operational6.8
Green Lane, Nempnett Thrubwell Solar Farmsolar farm9.1approved, not built7.1
Howgrove Farm, Green Lanesolar farm10approved, not built7.1
Garleys Wood Solar Parksolar farm5refused7.4
Chelwood Solar Farmsolar farm5operational8.2
Gypsy Lane, Burnett Solar PV Arrayssolar farm24.5refused8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3931, -2.6101).