Energy Projects Near You

Howgrove Farm, Green Lane (10 MW solar farm)

Howgrove Farm, Green Lane is a 10 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 November 2025, not yet built; the record was last updated on 9 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtstatus in REPD
9 December 2025record last updated
North Somersetcouncil area

Planning timeline

DateStage
28 May 2025Application submitted
3 November 2025Planning permission granted
3 November 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
9 December 2025
Operator or applicant
Greenvolt Power UK Limited
Planning authority
North Somerset
Planning application reference
25/02072/EFUL
Site area
13.6 ha
Address (REPD)
Parcel 0038, Green Lane, Nempnett Thrubwell, Bristol
Council area (by location)
North Somerset
Time to decision
23 weeks
Name in REPD
Howgrove Farm, Green Lane - Solar Panels
REPD reference
19109

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Green Lane, Nempnett Thrubwell Solar Farmsolar farm9.1approved, not built<0.1
Garleys Wood Solar Parksolar farm5refused4.5
Kitland Solar Farmsolar farm40approved, not built5.5
Yeowood Farmbattery storage49.9refused6.6
Iwood Lane Solar Farmsolar farm8operational6.9
East Dundry Lane, Norton Hawkfield Solar Farmsolar farm15application submitted7.1
Brinsea Green Farm, Brinsea Lanesolar farm30approved, not built7.2
Stowey Road, Stowey Solar Farmsolar farm49.9approved, not built7.9
East Dundry Lane, Norton Hawkfieldsolar farm15application submitted7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3553, -2.6918).