Solar, wind and battery projects near Bristol (BS40)
32 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS40 (North Somerset): 7 are waiting for a planning decision, 17 approved but not yet running, 4 operational. The largest live scheme is Station Road & Nye Road, Sandford (100 MW battery storage, application submitted on 12 June 2025, no decision recorded), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BS40
Projects of 1 MW and more (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Howgrove Farmsolar farm | solar farm | 4.7 | refused on appealupdated Mar 2016 | Sep 2014 | refused Jun 2015 | Mar 2016 | North Somerset | 0.9 |
| Howgrove Farm, Green Lanesolar farm | solar farm | 10 | approved, not builtupdated Dec 2025 | May 2025 | granted Nov 2025 | Dec 2025 | North Somerset | 1.0 |
| Green Lane, Nempnett Thrubwell Solar Farmsolar farm | solar farm | 9.1 | approved, not built may be out of dateupdated Jul 2025 | Feb 2022 | granted Oct 2022 | Jul 2025 | North Somerset | 1.0 |
| Lag Farmrooftop solar | rooftop solar | 1 | operationalupdated Jun 2020 | Dec 2019 | granted Jan 2020 | Jun 2020 | North Somerset | 2.4 |
| Garleys Wood Solar Parksolar farm | solar farm | 5 | refusedupdated Dec 2013 | Sep 2012 | refused Dec 2012 | Dec 2013 | North Somerset | 5.4 |
| Kitland Solar Farmsolar farm | solar farm | 40 | approved, not builtupdated Feb 2026 | May 2024 | granted Dec 2024 | Feb 2026 | North Somerset | 5.5 |
| Yeowood Farmbattery storage | battery storage | 49.9 | refusedupdated Jan 2025 | Aug 2024 | refused Dec 2024 | Jan 2025 | North Somerset | 6.7 |
| Iwood Lane Solar Farmsolar farm | solar farm | 8 | operationalupdated Jun 2015 | Dec 2013 | granted May 2014 | Jun 2015 | North Somerset | 7.0 |
| Brinsea Green Farm, Brinsea Lanesolar farm | solar farm | 30 | approved, not builtupdated Feb 2026 | Oct 2023 | granted Feb 2025 | Feb 2026 | North Somerset | 7.2 |
| Twin Elm Solar Farmsolar farm | solar farm | 1 | operationalupdated Dec 2013 | Mar 2012 | granted Jun 2012 | Dec 2013 | North Somerset | 7.3 |
| East Dundry Lane, Norton Hawkfield Solar Farmsolar farm | solar farm | 15 | application submittedupdated Dec 2025 | Jul 2025 | — | Dec 2025 | North Somerset | 7.7 |
| Hersey Gardenssolar farm | solar farm | 2 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | Bristol | 7.7 |
| Stowey Road, Stowey Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Nov 2024 | granted Jul 2025 | Feb 2026 | Bath and North East Somerset | 7.8 |
| The Strawberry Line, Brinsea Road Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Apr 2025 | granted Aug 2025 | Feb 2026 | North Somerset | 8.2 |
| East Dundry Lane, Norton Hawkfieldsolar farm | solar farm | 15 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Bath and North East Somerset | 8.3 |
| Oldbridge, Congresbury Solar Farmsolar farm | solar farm | 40 | application submittedupdated Jun 2026 | Jun 2025 | — | Jun 2026 | North Somerset | 8.6 |
| Congresbury Solar Farmsolar farm | solar farm | 7.1 | operationalupdated Mar 2016 | Jun 2014 | granted Nov 2014 | Mar 2016 | North Somerset | 9.2 |
| Yanel Farm, Churchill Green Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Apr 2026 | Jul 2022 | granted Apr 2024 | Apr 2026 | North Somerset | 9.4 |
| Station Road & Nye Road, Sandfordbattery storage | battery storage | 100 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | North Somerset | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bristol Airport Solar Farmsolar farm | solar farm | — | under constructionupdated May 2023 | — | — | May 2023 | North Somerset | 4.4 |
| Lower Stock Farm, Langfordbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | May 2024 | granted Dec 2024 | Feb 2026 | North Somerset | 5.5 |
| Langford - Roof Mounted Solar Photovoltaic Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2022 | Mar 2022 | granted Apr 2022 | Mar 2022 | North Somerset | 6.5 |
| Brinsea Green Farm, Brinsea Lanebattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Oct 2023 | granted Feb 2025 | Feb 2026 | North Somerset | 7.2 |
| East Dundry Lane, Norton Hawsfield Solar Farmsolar farm | solar farm | — | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | North Somerset | 7.5 |
| Coles Quarry, Church Townbattery storage | battery storage | 0.2 | refusedupdated Apr 2025 | Dec 2024 | refused Apr 2025 | Apr 2025 | North Somerset | 7.6 |
| The Strawberry Line, Brinsea Roadbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Apr 2025 | granted Aug 2025 | Feb 2026 | North Somerset | 8.2 |
| Cadbury Garden And Leisurerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2021 | Oct 2021 | granted Nov 2021 | Dec 2021 | North Somerset | 8.7 |
| Callow Rock Quarry, Shipham Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2024 | Sep 2024 | granted Nov 2024 | Dec 2024 | Somerset | 8.7 |
| Queens Road, Bishopsworthrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Bristol | 8.9 |
| Peterson Avenue, Hartcliffe Solar Photovoltaics PV equipmentrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Mar 2022 | Dec 2021 | Bristol | 9.1 |
| Hill Farm, East Dundry Road Solar Farmsolar farm | solar farm | — | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | Bristol | 9.8 |
| Bottle Yard Studios (TBY2)rooftop solar | rooftop solar | 1 | approved, not builtupdated Apr 2022 | Mar 2022 | granted Jun 2022 | Apr 2022 | Bristol | 10.0 |
Distance from the average position of the BS40 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 19 | 6 | 8 | 3 | 2 | 311 |
| Rooftop solar | 7 | 0 | 6 | 1 | 0 | 2.8 |
| Battery storage | 6 | 1 | 3 | 0 | 2 | 100 |
MW in pipeline: pending, approved and under-construction capacity.
How North Somerset decides solar, wind and battery applications
| Applications | North Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 7 (14%) | 19% |
| Solar refused | 2 of 38 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 5 of 10 | 16% |
| Median time from submission to decision | 14.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 2 | — |
All projects in North Somerset
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS40, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.