East Dundry Lane, Norton Hawkfield (15 MW solar farm)

East Dundry Lane, Norton Hawkfield is a 15 MW solar farm project in Bath and North East Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 2 July 2025, no decision recorded; the record was last updated on 1 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
application submittedstatus in REPD
1 September 2025record last updated
Bath and North East Somersetcouncil area

Planning timeline

DateStage
2 July 2025Application submitted

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
application submitted
Record last updated
1 September 2025
Operator or applicant
Enviromena
Planning authority
Bath and North East Somerset
Planning application reference
25/02595/FUL
Site area
14.0 ha
Address (REPD)
Parcel 3470, East Dundry Lane, Norton Hawkfield, Bristol
Council area (by location)
Bath and North East Somerset
Name in REPD
East Dundry Lane, Norton Hawkfield - Solar Panels
REPD reference
19368

Who decides

ApplicationsBath and North East SomersetUK
Decided applications (solar, wind, battery)1910,236
Refused5 (26%)19%
Solar refused5 of 1712%
Battery storage refused0 of 216%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Dundry Lane, Norton Hawkfield Solar Farmsolar farm15application submitted2.1
Stowey Road, Stowey Solar Farmsolar farm49.9approved, not built4.5
Chelwood Solar Farmsolar farm5operational6.1
Wilmington Farmsolar farm7.6refused6.6
Gypsy Lane, Burnett Solar PV Arrayssolar farm24.5refused7.1
The Flattssolar6.8refused7.2
Marksbury Plain Solar Parksolar farm15approved, not built7.3
Feeder Roadbattery storage20operational7.5
Philip Street Car Breakersbattery storage7.2approved, not built7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3816, -2.5858).