Solar, wind and battery projects near Bristol (BS39)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS39 (Bath and North East Somerset): 4 are waiting for a planning decision, 14 approved but not yet running, 5 operational. The largest live scheme is Stowey Road, Stowey Solar Farm (49.9 MW solar farm, approved on 24 July 2025, not yet built), 3.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BS39
Projects of 1 MW and more (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| The Flattssolar | solar | 6.8 | refusedupdated Aug 2014 | Mar 2014 | refused Jun 2014 | Aug 2014 | Bath and North East Somerset | 1.4 |
| Chelwood Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2016 | May 2014 | granted Sep 2014 | Jul 2016 | Bath and North East Somerset | 2.6 |
| Hunstrete (Wilmington Farm)solar farm | solar farm | 2.3 | operationalupdated Feb 2016 | Feb 2014 | granted Jun 2014 | Feb 2016 | Bath and North East Somerset | 3.3 |
| Wilmington Farmsolar farm | solar farm | 7.6 | refusedupdated Apr 2013 | Oct 2012 | refused Feb 2013 | Apr 2013 | Bath and North East Somerset | 3.5 |
| Stowey Road, Stowey Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Nov 2024 | granted Jul 2025 | Feb 2026 | Bath and North East Somerset | 3.6 |
| Marksbury Plain Solar Parksolar farm | solar farm | 15 | approved, not built may be out of dateupdated Mar 2025 | Jan 2022 | granted Jul 2022 | Mar 2025 | Bath and North East Somerset | 3.7 |
| Parcel 2882, Water Lane Solar Farmsolar farm | solar farm | 9.2 | approved, not builtupdated Jun 2025 | Oct 2024 | granted Jun 2025 | Jun 2025 | Bath and North East Somerset | 4.6 |
| Solar Park - Whitchurch Farmsolar farm | solar farm | 6.5 | operationalupdated Apr 2014 | Apr 2012 | granted Nov 2012 | Apr 2014 | Somerset | 5.4 |
| Midsomer Nortonbattery storage | battery storage | 6 | under constructionupdated Aug 2022 | Jul 2021 | granted Dec 2022 | Aug 2022 | Bath and North East Somerset | 6.0 |
| Fairy Hill, Compton Dando Solar Farmsolar farm | solar farm | 2.1 | approved, not builtupdated Dec 2025 | Dec 2023 | granted Jul 2025 | Dec 2025 | Bath and North East Somerset | 6.2 |
| East Dundry Lane, Norton Hawkfieldsolar farm | solar farm | 15 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Bath and North East Somerset | 7.0 |
| Gypsy Lane, Burnett Solar PV Arrayssolar farm | solar farm | 24.5 | refusedupdated Jan 2026 | Jul 2024 | refused Sep 2025 | Jan 2026 | Bath and North East Somerset | 7.8 |
| Shooters Bottom Solar Parksolar farm | solar farm | 7 | operationalupdated Apr 2014 | Mar 2011 | granted Jul 2011 | Apr 2014 | Somerset | 8.5 |
| Shooters Bottom Wind Parkwind turbine | wind turbine | 2 | operationalupdated May 2009 | Sep 2003 | granted May 2006 | May 2009 | Somerset | 8.9 |
| New Tyning Farmsolar farm | solar farm | 5.8 | refused on appealupdated Nov 2014 | Jun 2013 | refused Jan 2014 | Nov 2014 | Somerset | 9.0 |
| East Dundry Lane, Norton Hawkfield Solar Farmsolar farm | solar farm | 15 | application submittedupdated Dec 2025 | Jul 2025 | — | Dec 2025 | North Somerset | 9.0 |
| Ash Farm, Charlton Roadbattery storage | battery storage | 10 | approved, not builtupdated Feb 2025 | May 2024 | granted Dec 2024 | Feb 2025 | Somerset | 9.1 |
| Ash Farm, Charlton Roadsolar farm | solar farm | 5 | approved, not builtupdated Feb 2025 | May 2024 | granted Dec 2024 | Feb 2025 | Somerset | 9.1 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Paulton House, Old Millsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Feb 2025 | Feb 2025 | Bath and North East Somerset | 4.4 |
| Parcel 2882, Water Lanebattery storage | battery storage | — | approved, not builtupdated Jun 2025 | Oct 2024 | granted Jun 2025 | Jun 2025 | Bath and North East Somerset | 4.6 |
| Bridges Electrical Engineers, Second Avenuerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Bath and North East Somerset | 7.3 |
| Optima Products, Mill Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | Bath and North East Somerset | 7.8 |
| Hill Farm, East Dundry Road Solar Farmsolar farm | solar farm | — | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | Bristol | 9.1 |
| Robinson House Nursing Home, Sturminster Road Solar Photovoltaicsrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Bristol | 9.3 |
| East Dundry Lane, Norton Hawsfield Solar Farmsolar farm | solar farm | — | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | North Somerset | 9.3 |
| Wellsway School, Chandag Road PV Arraysrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Oct 2024 | Jul 2024 | granted Sep 2024 | Oct 2024 | Bath and North East Somerset | 9.6 |
| Peterson Avenue, Hartcliffe Solar Photovoltaics PV equipmentrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Mar 2022 | Dec 2021 | Bristol | 9.7 |
Distance from the average position of the BS39 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 16 | 4 | 5 | 4 | 3 | 111 |
| Rooftop solar | 6 | 0 | 6 | 0 | 0 | 1.4 |
| Solar | 1 | 0 | 0 | 0 | 1 | 0 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 3 | 0 | 3 | 0 | 0 | 16 |
MW in pipeline: pending, approved and under-construction capacity.
How Bath and North East Somerset decides solar, wind and battery applications
| Applications | Bath and North East Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 5 (26%) | 19% |
| Solar refused | 5 of 17 | 12% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 17.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
All projects in Bath and North East Somerset
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS39, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.