Energy Projects Near You

Shooters Bottom Solar Park (7 MW)

Shooters Bottom Solar Park is a 7 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 5 February 2014; the record was last updated on 3 April 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
3 April 2014record last updated
Somersetcouncil area

Planning timeline

DateStage
23 March 2011Application submitted
28 July 2011Planning permission granted
5 February 2014Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
3 April 2014
Operator or applicant
Anesco
Planning authority
Somerset
Planning application reference
2011/0529
Address (REPD)
Townsend Lane, Chewton, Mendip
Council area (by location)
Somerset
Time to decision
18 weeks
REPD reference
1575

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Park - Whitchurch Farmsolar farm6.5operational4.8
Crapnell Farm Solar Farmsolar farm5.4operational5.6
Parcel 2882, Water Lane Solar Farmsolar farm9.2approved, not built8.0
Lodge Farm Solar Farmsolar farm5under construction8.2
Ash Farm, Charlton Roadbattery storage10approved, not built8.5
Worminster Downsolar farm15refused on appeal8.8
Midsomer Nortonbattery storage6under construction8.8
Hurlingpot Farmsolar farm5.3refused on appeal9.0
Stowey Road, Stowey Solar Farmsolar farm49.9approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2588, -2.5864).