Solar, wind and battery projects near Wells (BA5)
16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BA5 (Somerset): 1 is waiting for a planning decision, 6 approved but not yet running, 6 operational. The largest live scheme is Charlie Bighams Quarry Kitchen, Dulcote Hill Lane (2.2 MW solar farm, approved on 23 September 2025, not yet built), 2.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BA5
Projects of 1 MW and more (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Charlie Bighams Quarry Kitchen, Dulcote Hill Lanesolar farm | solar farm | 2.2 | approved, not builtupdated Oct 2025 | Nov 2024 | granted Sep 2025 | Oct 2025 | Somerset | 2.5 |
| Worminster Downsolar farm | solar farm | 15 | refused on appealupdated Oct 2015 | Jun 2014 | refused Aug 2014 | Oct 2015 | Somerset | 3.6 |
| Pitts Farmsolar farm | solar farm | 2.6 | operationalupdated Oct 2014 | Apr 2013 | granted Jun 2013 | Oct 2014 | Somerset | 4.9 |
| Crapnell Farm Solar Farmsolar farm | solar farm | 5.4 | operationalupdated May 2014 | Jul 2013 | granted Sep 2013 | May 2014 | Somerset | 5.4 |
| Shooters Bottom Wind Parkwind turbine | wind turbine | 2 | operationalupdated May 2009 | Sep 2003 | granted May 2006 | May 2009 | Somerset | 6.8 |
| Shooters Bottom Solar Parksolar farm | solar farm | 7 | operationalupdated Apr 2014 | Mar 2011 | granted Jul 2011 | Apr 2014 | Somerset | 7.0 |
| Norwood Park Farmsolar farm | solar farm | 7 | refused on appealupdated Feb 2016 | Aug 2013 | refused Oct 2014 | Feb 2016 | Somerset | 7.4 |
| Hawkers Farmsolar farm | solar farm | 9.5 | operationalupdated Apr 2015 | Nov 2014 | granted Feb 2015 | Apr 2015 | Somerset | 7.7 |
| New Row Farmsolar farm | solar farm | 3.9 | operationalupdated Oct 2014 | Aug 2013 | granted Nov 2013 | Oct 2014 | Somerset | 8.9 |
| Middle Drove and Porchestall Drovesolar farm | solar farm | 1.2 | refusedupdated Oct 2025 | Jun 2025 | refused Oct 2025 | Oct 2025 | Somerset | 9.0 |
| Bays Lane, Gurney Sladesolar farm | solar farm | 2 | application submittedupdated Nov 2025 | Sep 2025 | — | Nov 2025 | Somerset | 9.3 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Warren Farm, Masburywind turbine | wind turbine | 0.3 | approved, not builtupdated Dec 2025 | Jan 2025 | granted Nov 2025 | Dec 2025 | Somerset | 6.7 |
| Worthy Lane, Piltonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Somerset | 7.6 |
| Showerings Cider Mill, Kilver Streetrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Somerset | 8.6 |
| Showerings Cider Mill, Kilver Streetrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jun 2025 | Jul 2025 | Somerset | 8.6 |
| Charlton Factory, Kilver Streetrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jun 2025 | Jul 2025 | Somerset | 8.7 |
Distance from the average position of the BA5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 1 | 1 | 5 | 3 | 4.2 |
| Rooftop solar | 4 | 0 | 4 | 0 | 0 | 1.1 |
| Wind turbine | 2 | 0 | 1 | 1 | 0 | 0.3 |
MW in pipeline: pending, approved and under-construction capacity.
How Somerset decides solar, wind and battery applications
| Applications | Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 185 | 10,236 |
| Refused | 46 (25%) | 19% |
| Solar refused | 34 of 153 | 12% |
| Onshore wind refused | 9 of 10 | 45% |
| Battery storage refused | 3 of 22 | 16% |
| Median time from submission to decision | 14.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 17 / 9 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.