Norwood Park Farm (7 MW solar farm)

Norwood Park Farm is a 7 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 6 January 2016; the record was last updated on 5 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
refused on appealstatus in REPD
5 February 2016record last updated
Somersetcouncil area

Planning timeline

DateStage
27 August 2013Application submitted
3 October 2014Refused by the planning authority
20 May 2015Appeal lodged
6 January 2016Appeal refused

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
refused on appeal
Record last updated
5 February 2016
Operator or applicant
juwi Renewable Energies
Planning authority
Somerset
Planning application reference
2013/1749
Appeal reference
APP/Q3305/W/15/3011465
Address (REPD)
Norwood Park Farm, Wick Lane, Glastonbury
Council area (by location)
Somerset
Time to decision
57 weeks
REPD reference
2134

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Park Wood Solar Farmsolar farm5operational4.8
Worminster Downsolar farm15refused on appeal5.3
Higher Hill Farmsolar farm5operational8.0
Lower Easton Farmsolar farm13.5refused9.8
Pylle Southern solar park (Lower Easton Farm)solar farm5operational9.8
Crapnell Farm Solar Farmsolar farm5.4operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1481, -2.6797).