Hawkers Farm (9.5 MW solar farm)

Hawkers Farm is a 9.5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2015; the record was last updated on 16 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.5 MWsolar farm
operationalstatus in REPD
16 April 2015record last updated
Somersetcouncil area

Planning timeline

DateStage
5 November 2014Application submitted
17 February 2015Planning permission granted
18 February 2015Construction started
23 March 2015Operational

Project details

Technology
solar farm
Capacity
9.5 MW
Status (REPD)
operational
Record last updated
16 April 2015
Operator or applicant
Greenfields (A)
Planning authority
Somerset
Planning application reference
50/14/00095
Site area
2.5 ha
Address (REPD)
Hawkers Farm, Yeo Moor Drove, Theale, Wedmore
Council area (by location)
Somerset
Time to decision
15 weeks
REPD reference
4757

Earlier applications for this site

ApplicationMWSubmittedOutcome
Hawkers Farm 50/14/000691226 June 2014replaced by a revised application

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2244, -2.7639).