Lodge Farm Solar Farm (5 MW)

Lodge Farm Solar Farm is a 5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 6 October 2015; the record was last updated on 3 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
under constructionstatus in REPD
3 August 2020record last updated
Somersetcouncil area

Planning timeline

DateStage
9 May 2011Application submitted
6 December 2011Planning permission granted
6 October 2015Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
under construction
Record last updated
3 August 2020
Operator or applicant
Ecotricity
Planning authority
Somerset
Planning application reference
2011/0765
Address (REPD)
Lodge Farm, Doulting, Shepton Mallet, Somerset
Council area (by location)
Somerset
Time to decision
30 weeks
REPD reference
1611

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hurlingpot Farmsolar farm5.3refused on appeal1.8
Crapnell Farm Solar Farmsolar farm5.4operational5.1
The Royal Bath & West Showground Solar Farmsolar farm5abandoned6.3
Ash Farm, Charlton Roadbattery storage10approved, not built6.6
Lower Easton Farmsolar farm13.5refused6.9
Pylle Southern solar park (Lower Easton Farm)solar farm5operational6.9
Shooters Bottom Solar Parksolar farm7operational8.2
Solar Park - Whitchurch Farmsolar farm6.5operational8.4
Holwell Hillsolar farm6operational8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.205, -2.5056).