Hurlingpot Farm (5.3 MW solar farm)

Hurlingpot Farm is a 5.3 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 19 December 2013; the record was last updated on 20 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.3 MWsolar farm
refused on appealstatus in REPD
20 January 2014record last updated
Somersetcouncil area

Planning timeline

DateStage
13 August 2012Application submitted
11 January 2013Refused by the planning authority
19 December 2013Appeal refused

Project details

Technology
solar farm
Capacity
5.3 MW
Status (REPD)
refused on appeal
Record last updated
20 January 2014
Operator or applicant
AEE Renewables
Planning authority
Somerset
Planning application reference
2012/1562
Site area
13.9 ha
Address (REPD)
Doulting
Council area (by location)
Somerset
Time to decision
22 weeks
REPD reference
1599

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lodge Farm Solar Farmsolar farm5under construction1.8
The Royal Bath & West Showground Solar Farmsolar farm5abandoned4.6
Crapnell Farm Solar Farmsolar farm5.4operational4.8
Lower Easton Farmsolar farm13.5refused5.2
Pylle Southern solar park (Lower Easton Farm)solar farm5operational5.2
Worminster Downsolar farm15refused on appeal8.0
Ash Farm, Charlton Roadbattery storage10approved, not built8.4
Shooters Bottom Solar Parksolar farm7operational9.0
Holwell Hillsolar farm6operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1905, -2.516).