Energy Projects Near You

Parcel 2882, Water Lane Solar Farm (9.2 MW)

Parcel 2882, Water Lane Solar Farm is a 9.2 MW solar farm project in Bath and North East Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 June 2025, not yet built; the record was last updated on 12 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWsolar farm
approved, not builtstatus in REPD
12 June 2025record last updated
Bath and North East Somersetcouncil area

Planning timeline

DateStage
16 October 2024Application submitted
5 June 2025Planning permission granted
5 June 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
9.2 MW
Status (REPD)
approved, not built
Record last updated
12 June 2025
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
Bath and North East Somerset
Planning application reference
24/03894/FUL
Site area
15.6 ha
Address (REPD)
S/O Water Lane, Bristol
Council area (by location)
Bath and North East Somerset
Time to decision
33 weeks
Name in REPD
Parcel 2882, Water Lane - Solar Farm
REPD reference
17422

Who decides

ApplicationsBath and North East SomersetUK
Decided applications (solar, wind, battery)1910,236
Refused5 (26%)19%
Solar refused5 of 1712%
Battery storage refused0 of 216%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Midsomer Nortonbattery storage6under construction1.5
Solar Park - Whitchurch Farmsolar farm6.5operational3.2
New Tyning Farmsolar farm5.8refused on appeal4.4
The Flattssolar6.8refused4.4
Ash Farm, Charlton Roadbattery storage10approved, not built4.7
Marksbury Plain Solar Parksolar farm15approved, not built5.9
Chelwood Solar Farmsolar farm5operational5.9
Wilmington Farmsolar farm7.6refused6.2
Stowey Road, Stowey Solar Farmsolar farm49.9approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2977, -2.4892).