Energy Projects Near You

Renewable energy projects in Bath and North East Somerset

20 solar, wind or battery projects of 150 kW or more are located in Bath and North East Somerset (REPD, July 2026 extract): 1 pending, 13 approved but not running, 2 operational and 4 refused. The council refused 5 of 19 decided applications (26%; UK 19%), with a median 17 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20projects in the council area
1awaiting a decision
13approved, not running
26%of decisions refused

How Bath and North East Somerset decides

ApplicationsBath and North East SomersetUK
Decided applications (solar, wind, battery)1910,236
Refused5 (26%)19%
Solar refused5 of 1712%
Battery storage refused0 of 216%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Projects in Bath and North East Somerset

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Stowey Road, Stowey Solar Farmsolar farmsolar farm49.9approved, not builtupdated Feb 2026Nov 2024granted Jul 2025Feb 2026
Gypsy Lane, Burnett Solar PV Arrayssolar farmsolar farm24.5refusedupdated Jan 2026Jul 2024refused Sep 2025Jan 2026
Marksbury Plain Solar Parksolar farmsolar farm15approved, not built may be out of dateupdated Mar 2025Jan 2022granted Jul 2022Mar 2025
East Dundry Lane, Norton Hawkfieldsolar farmsolar farm15application submittedupdated Sep 2025Jul 2025—Sep 2025
Parcel 2882, Water Lane Solar Farmsolar farmsolar farm9.2approved, not builtupdated Jun 2025Oct 2024granted Jun 2025Jun 2025
Wilmington Farmsolar farmsolar farm7.6refusedupdated Apr 2013Oct 2012refused Feb 2013Apr 2013
The Flattssolarsolar6.8refusedupdated Aug 2014Mar 2014refused Jun 2014Aug 2014
Midsomer Nortonbattery storagebattery storage6under constructionupdated Aug 2022Jul 2021granted Dec 2022Aug 2022
Chelwood Solar Farmsolar farmsolar farm5operationalupdated Jul 2016May 2014granted Sep 2014Jul 2016
Hunstrete (Wilmington Farm)solar farmsolar farm2.3operationalupdated Feb 2016Feb 2014granted Jun 2014Feb 2016
Fairy Hill, Compton Dando Solar Farmsolar farmsolar farm2.1approved, not builtupdated Dec 2025Dec 2023granted Jul 2025Dec 2025
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Bridges Electrical Engineers, Second Avenuerooftop solarrooftop solar0.3approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024
Royal United Hospital, Combe Parkrooftop solarrooftop solar0.3approved, not builtupdated Jun 2025Mar 2025granted Apr 2025Jun 2025
Optima Products, Mill Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023
King Edwards School, North Roadrooftop solarrooftop solar0.2under constructionupdated May 2023Apr 2023—May 2023
Paulton House, Old Millsrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Feb 2025Feb 2025
Wellsway School, Chandag Road PV Arraysrooftop solarrooftop solar0.1approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024
Bath Sports And Leisure Centre, North Parade Roadrooftop solarrooftop solar—under constructionupdated Feb 2025Aug 2024granted Oct 2024Feb 2025
Parcel 2882, Water Lanebattery storagebattery storage—approved, not builtupdated Jun 2025Oct 2024granted Jun 2025Jun 2025
LiveWest Homesrooftop solarrooftop solar—refusedupdated Jun 2026Mar 2026refused May 2026Jun 2026

Postcode districts in Bath and North East Somerset

DistrictProjects within 10 kmPendingApprovedOperational
BA111052
BA2170103
BA3332169
BS31376224
BS39274145

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Bath and North East Somerset by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.