Gypsy Lane, Burnett Solar PV Arrays (24.5 MW)

Gypsy Lane, Burnett Solar PV Arrays is a 24.5 MW solar farm project in Bath and North East Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 25 September 2025; the record was last updated on 13 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24.5 MWsolar farm
refusedstatus in REPD
13 January 2026record last updated
Bath and North East Somersetcouncil area

Planning timeline

DateStage
1 July 2024Application submitted
25 September 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
24.5 MW
Status (REPD)
refused
Record last updated
13 January 2026
Operator or applicant
Conrad Energy (Developments) Limited
Planning authority
Bath and North East Somerset
Planning application reference
24/02489/EFUL
Site area
28.2 ha
Address (REPD)
Gypsy Lane, Burnett, Keynsham, Bristol
Council area (by location)
Bath and North East Somerset
Time to decision
64 weeks
Name in REPD
Gypsy Lane, Burnett - Solar PV Arrays
REPD reference
16791

Who decides

ApplicationsBath and North East SomersetUK
Decided applications (solar, wind, battery)1910,236
Refused5 (26%)19%
Solar refused5 of 1712%
Battery storage refused0 of 216%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wilmington Farmsolar farm7.6refused4.4
Marksbury Plain Solar Parksolar farm15approved, not built4.6
Chelwood Solar Farmsolar farm5operational5.2
The Flattssolar6.8refused6.7
East Dundry Lane, Norton Hawkfieldsolar farm15application submitted7.1
Feeder Roadbattery storage20operational8.4
Philip Street Car Breakersbattery storage7.2approved, not built8.6
Stowey Road, Stowey Solar Farmsolar farm49.9approved, not built8.6
East Dundry Lane, Norton Hawkfield Solar Farmsolar farm15application submitted8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.391, -2.485).