Renewable energy projects in Wiltshire
167 solar, wind or battery projects of 150 kW or more are located in Wiltshire (REPD, July 2026 extract): 20 pending, 77 approved but not running, 49 operational and 8 refused. The council refused 18 of 140 decided applications (13%; UK 19%), with a median 21 weeks from submission to decision.
167projects in the council area
20awaiting a decision
77approved, not running
13%of decisions refused
How Wiltshire decides
| Applications | Wiltshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 140 | 10,236 |
| Refused | 18 (13%) | 19% |
| Solar refused | 13 of 110 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 4 of 29 | 16% |
| Median time from submission to decision | 20.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 7 | — |
Projects in Wiltshire
Projects of 1 MW and more (100)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Lime Down Solar Projectsolar farm | solar farm | 500 | application submittedupdated Jun 2026 | Oct 2025 | — | Jun 2026 |
| Lime Downbattery storage | battery storage | 500 | application submittedupdated Jun 2026 | Oct 2025 | — | Jun 2026 |
| Brockleaze, Neston Park Estatebattery storage | battery storage | 450 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 |
| Norrington Gate Farm, Broughton Giffordbattery storage | battery storage | 150 | approved, not built may be out of dateupdated Jul 2022 | Jun 2022 | granted Jan 2023 | Jul 2022 |
| Bradenstoke solar parksolar farm | solar farm | 69.8 | operationalupdated Jul 2024 | Jul 2014 | granted Nov 2014 | Jul 2024 |
| Melksham Substation East Storagebattery storage | battery storage | 50 | operationalupdated Nov 2022 | May 2017 | granted Apr 2019 | Nov 2022 |
| Stonehill Energy Storage / Lower Minetybattery storage | battery storage | 50 | operationalupdated Mar 2026 | Nov 2019 | granted Feb 2020 | Mar 2026 |
| Fairholme, Minetybattery storage | battery storage | 50 | approved, not builtupdated Jul 2024 | Jul 2022 | granted May 2024 | Jul 2024 |
| Stonehill Energy Storagebattery storage | battery storage | 50 | approved, not builtupdated May 2025 | Jul 2022 | granted May 2025 | May 2025 |
| Stonehill Energy Storage / Upper Minetybattery storage | battery storage | 50 | operationalupdated Mar 2026 | Jun 2017 | granted Sep 2017 | Mar 2026 |
| Stonehill Energy Storage / Upper Minetybattery storage | battery storage | 50 | operationalupdated Mar 2026 | — | granted Jul 2018 | Mar 2026 |
| Minety Northbattery storage | battery storage | 50 | abandonedupdated Sep 2022 | May 2017 | — | Sep 2022 |
| Minety Southbattery storage | battery storage | 50 | operationalupdated Aug 2020 | May 2017 | granted Sep 2017 | Aug 2020 |
| Minety South 2battery storage | battery storage | 50 | operationalupdated Mar 2026 | Mar 2021 | granted Nov 2021 | Mar 2026 |
| Ravensroost Farm, Minetybattery storage | battery storage | 49.9 | approved, not builtupdated Nov 2024 | Jun 2022 | refused Mar 2024 | Nov 2024 |
| Snarlton Farmbattery storage | battery storage | 49.9 | abandonedupdated Jan 2020 | Mar 2019 | — | Jan 2020 |
| Down Barn Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated May 2023 | Nov 2019 | granted Apr 2020 | May 2023 |
| National Grid Minety Substationbattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Jul 2024 | Aug 2020 | granted Jan 2021 | Jul 2024 |
| Wick Farm Melksham Substationsolar farm | solar farm | 49.9 | under constructionupdated May 2025 | Aug 2020 | granted Dec 2021 | May 2025 |
| Crudwell Road Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Mar 2021 | granted Aug 2023 | Feb 2026 |
| Forest Gate Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Jun 2021 | Jun 2021 | granted Mar 2023 | Jun 2021 |
| Leigh Delamere Solar farm & Battery storagesolar farm | solar farm | 49.9 | under constructionupdated Aug 2025 | Jun 2021 | granted Aug 2022 | Aug 2025 |
| Studley Farm Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Jul 2022 | Sep 2021 | granted Jun 2022 | Jul 2022 |
| Potterne Park Farm, Potterne Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated May 2026 | Dec 2023 | granted Apr 2026 | May 2026 |
| Snarlton Farm (Melksham solar farm)solar farm | solar farm | 49.6 | operationalupdated Feb 2017 | Nov 2013 | granted Jun 2015 | Feb 2017 |
| Salisbury Substationbattery storage | battery storage | 49.5 | operationalupdated Jun 2026 | Aug 2019 | granted Dec 2021 | Jun 2026 |
| Minety Substationsolar farm | solar farm | 40 | approved, not built may be out of dateupdated Jul 2022 | Apr 2020 | granted Apr 2022 | Jul 2022 |
| Forest Gate Solar Farm & Battery Storagebattery storage | battery storage | 40 | approved, not built may be out of dateupdated Jun 2021 | Jun 2021 | granted Mar 2023 | Jun 2021 |
| Leigh Delamere Solar farm & Battery storagebattery storage | battery storage | 40 | under constructionupdated Aug 2025 | Jun 2021 | granted Aug 2022 | Aug 2025 |
| Red Barn Solar Farm & Battery Storagesolar farm | solar farm | 40 | approved, not builtupdated Feb 2026 | Oct 2023 | granted Jan 2025 | Feb 2026 |
| Red Barn Solar Farm & Battery Storagebattery storage | battery storage | 40 | approved, not builtupdated Feb 2026 | Oct 2023 | granted Jan 2025 | Feb 2026 |
| Blackthorn Solar Farmsolar farm | solar farm | 40 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 |
| Water Eaton Farm / Port Farmsolar farm | solar farm | 34.8 | operationalupdated Mar 2018 | Apr 2014 | granted Aug 2014 | Mar 2018 |
| Storridge Road Solar Farmsolar farm | solar farm | 31 | approved, not builtupdated Feb 2022 | Nov 2021 | granted Oct 2023 | Feb 2022 |
| Beech Tree Solar Farmsolar farm | solar farm | 30 | approved, not builtupdated Aug 2025 | Nov 2023 | granted Jul 2025 | Aug 2025 |
| Hoopers Pool, Southwicksolar farm | solar farm | 30 | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 |
| Whaddon Lane, Hilpertonsolar farm | solar farm | 25 | approved, not built may be out of dateupdated Sep 2023 | May 2021 | granted Apr 2022 | Sep 2023 |
| Swallett Energy Parksolar farm | solar farm | 23 | approved, not builtupdated Feb 2026 | Dec 2023 | granted Jan 2026 | Feb 2026 |
| Cockhill Solar Farmsolar farm | solar farm | 20 | operationalupdated Jul 2015 | Jun 2014 | granted Aug 2014 | Jul 2015 |
| Tiddlywink Barn Battery Storage Power Plantbattery storage | battery storage | 20 | abandonedupdated Jun 2022 | Aug 2021 | — | Jun 2022 |
| Mopes Lane, Purton Solar Farmsolar farm | solar farm | 20 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Apr 2023 | Dec 2021 |
| East Codford Solar Farm Extension Phase 3solar farm | solar farm | 18 | operationalupdated Jun 2023 | Apr 2019 | granted Dec 2020 | Jun 2023 |
| Whaddon Lane, Hilpertonbattery storage | battery storage | 18 | approved, not built may be out of dateupdated Sep 2023 | May 2021 | granted Apr 2022 | Sep 2023 |
| Codford Solar Farm Phase 4solar farm | solar farm | 18 | approved, not builtupdated Feb 2026 | May 2023 | granted Jul 2024 | Feb 2026 |
| Stokes Marsh Farmsolar farm | solar farm | 16.6 | operationalupdated Nov 2017 | Aug 2013 | granted Dec 2013 | Nov 2017 |
| Bake Farmsolar farm | solar farm | 16.1 | application withdrawnupdated Jul 2014 | Dec 2013 | — | Jul 2014 |
| Blounts Court Farm, Potternesolar farm | solar farm | 15 | refusedupdated Jul 2025 | Jun 2024 | refused May 2025 | Jul 2025 |
| Lodge Farm (Poulshot)solar farm | solar farm | 14.5 | operationalupdated Apr 2015 | Oct 2013 | granted Feb 2014 | Apr 2015 |
| Marsh Farmsolar farm | solar farm | 14 | operationalupdated Feb 2017 | Jul 2012 | granted Jan 2013 | Feb 2017 |
| Roundponds Farm Solar Parksolar farm | solar farm | 13.5 | operationalupdated Apr 2015 | Jan 2014 | granted May 2014 | Apr 2015 |
| Solar Farm at Townsend Farmsolar farm | solar farm | 13.5 | approved, not builtupdated Jan 2026 | Jan 2025 | granted Dec 2025 | Jan 2026 |
| Leechpool Farm, Norrington Battery Storagebattery storage | battery storage | 13 | permission expiredupdated Aug 2020 | May 2018 | — | Aug 2020 |
| Malmesbury Road Solar Farmsolar farm | solar farm | 13 | approved, not builtupdated Mar 2022 | Sep 2021 | granted Oct 2023 | Mar 2022 |
| Boscombe Airfieldsolar farm | solar farm | 12.3 | operationalupdated Apr 2015 | Jun 2014 | granted Nov 2014 | Apr 2015 |
| Castle Combe Circuitsolar farm | solar farm | 12 | operationalupdated Apr 2015 | Jul 2014 | granted Nov 2014 | Apr 2015 |
| Little Chalfield Solar Farmsolar farm | solar farm | 12 | refused on appealupdated May 2015 | May 2014 | refused Sep 2014 | May 2015 |
| Spittleborough Farmsolar farm | solar farm | 12 | operationalupdated Aug 2014 | Jul 2013 | granted Dec 2013 | Aug 2014 |
| Bentham House Farm, Mopes Lane Solar Farmsolar farm | solar farm | 12 | approved, not builtupdated Feb 2026 | Sep 2024 | granted Jun 2025 | Feb 2026 |
| Battens Farm Solar Parksolar farm | solar farm | 11 | operationalupdated May 2014 | May 2013 | granted Aug 2013 | May 2014 |
| Norrington Common Solar Farmsolar farm | solar farm | 10 | operationalupdated Feb 2017 | Nov 2012 | granted Apr 2013 | Feb 2017 |
| Minety Substationbattery storage | battery storage | 10 | approved, not built may be out of dateupdated Jul 2022 | Apr 2020 | granted Apr 2022 | Jul 2022 |
| Park Farmbattery storage | battery storage | 10 | permission expiredupdated Apr 2021 | Mar 2018 | granted May 2018 | Apr 2021 |
| Solar Farm at East of Battens Farmsolar farm | solar farm | 10 | approved, not builtupdated Jan 2026 | Oct 2024 | granted Sep 2025 | Jan 2026 |
| High Penn Solar Parksolar farm | solar farm | 9.6 | operationalupdated Sep 2014 | Feb 2013 | granted Oct 2013 | Sep 2014 |
| Marsh Farm Hilpertonsolar farm | solar farm | 9.1 | operationalupdated Sep 2018 | Jan 2014 | granted Apr 2014 | Sep 2018 |
| Braydon Manor Farmsolar farm | solar farm | 8.7 | operationalupdated Jul 2016 | Jun 2013 | granted Oct 2013 | Jul 2016 |
| Mill Farm, Teffontbattery storage | battery storage | 8.5 | approved, not builtupdated Apr 2024 | Oct 2023 | granted Mar 2024 | Apr 2024 |
| Bentham Farmsolar farm | solar farm | 8 | operationalupdated Jul 2015 | Oct 2013 | granted Dec 2014 | Jul 2015 |
| Cooles Farm, Minety Solar Park/Battery Storagesolar farm | solar farm | 8 | application submitted may be out of dateupdated Dec 2022 | Nov 2022 | — | Dec 2022 |
| Deptford Farm solar parksolar farm | solar farm | 7.8 | refusedupdated Mar 2014 | May 2013 | refused Dec 2013 | Mar 2014 |
| Rodbourne Rail Farm Solar Parksolar farm | solar farm | 7.6 | operationalupdated Mar 2014 | May 2012 | granted Nov 2012 | Mar 2014 |
| Newnton Dairy Farmsolar farm | solar farm | 7.2 | operationalupdated Apr 2014 | Jun 2013 | granted Sep 2013 | Apr 2014 |
| Rudge Farm Solar Farmsolar farm | solar farm | 7 | operationalupdated May 2016 | Jul 2012 | granted Dec 2012 | May 2016 |
| Hullavington Solar Parksolar farm | solar farm | 7 | operationalupdated May 2016 | May 2013 | granted Nov 2013 | May 2016 |
| Land at East Farmsolar farm | solar farm | 6.8 | operationalupdated Jun 2014 | Jan 2013 | granted Mar 2013 | Jun 2014 |
| Land at Poles Hole Farmsolar farm | solar farm | 6.8 | operationalupdated Jul 2018 | May 2015 | granted Oct 2015 | Jul 2018 |
| Somerford Farm, Brinkworthbattery storage | battery storage | 6.6 | approved, not builtupdated Oct 2024 | Apr 2022 | granted Oct 2024 | Oct 2024 |
| Manor Farm (Wiltshire)solar farm | solar farm | 6.3 | operationalupdated Mar 2017 | Mar 2014 | granted Dec 2014 | Mar 2017 |
| Blenches Millsolar farm | solar farm | 6.1 | operationalupdated Jul 2018 | Nov 2012 | granted Nov 2013 | Jul 2018 |
| Land at East Farm - extensionsolar farm | solar farm | 6 | operationalupdated Jul 2016 | Oct 2013 | granted Jan 2014 | Jul 2016 |
| East Farm (Clay Pit Hill) - Extension IIsolar farm | solar farm | 6 | application withdrawnupdated Dec 2018 | Apr 2018 | — | Dec 2018 |
| Sands Farm Quarry, Low Lanesolar farm | solar farm | 6 | application submitted may be out of dateupdated Mar 2024 | Feb 2024 | — | Mar 2024 |
| Malmesbury Solarsolar farm | solar farm | 5 | operationalupdated Mar 2013 | Mar 2011 | granted May 2011 | Mar 2013 |
| Kingston Farmsolar farm | solar farm | 5 | operationalupdated Mar 2013 | Mar 2011 | granted May 2011 | Mar 2013 |
| Lake Farmsolar farm | solar farm | 5 | operationalupdated Mar 2013 | Jan 2011 | granted Apr 2011 | Mar 2013 |
| Wickfield Farmsolar farm | solar farm | 5 | operationalupdated Jul 2017 | Mar 2014 | granted Jun 2014 | Jul 2017 |
| Rock Farm / Goldborough Farm (Rookwood)solar farm | solar farm | 5 | operationalupdated Mar 2015 | Dec 2013 | granted Jul 2014 | Mar 2015 |
| Bake Farm Solar Farmsolar farm | solar farm | 5 | operationalupdated Jun 2017 | Nov 2014 | granted Mar 2015 | Jun 2017 |
| Trowle Commonsolar farm | solar farm | 5 | operationalupdated Apr 2016 | Jan 2015 | granted Jun 2015 | Apr 2016 |
| Land West Side of Axe and Cleaver Lanesolar farm | solar farm | 5 | operationalupdated May 2016 | May 2015 | granted Aug 2015 | May 2016 |
| Park Grounds Farmsolar farm | solar farm | 5 | abandonedupdated Apr 2017 | Aug 2015 | granted Dec 2015 | Apr 2017 |
| Lower End Farmsolar farm | solar farm | 4.9 | operationalupdated Aug 2017 | Mar 2014 | granted Aug 2014 | Aug 2017 |
| Brook Hall Farmsolar farm | solar farm | 4.7 | operationalupdated May 2016 | Jun 2015 | granted Nov 2015 | May 2016 |
| Land At Moor Lane Farmsolar farm | solar farm | 4.5 | refusedupdated Sep 2016 | Aug 2015 | refused Aug 2016 | Sep 2016 |
| Bollands Hillsolar | solar | 4 | refused on appealupdated Oct 2015 | Apr 2014 | refused Sep 2014 | Oct 2015 |
| Land north of Ashton Roadsolar farm | solar farm | 4 | operationalupdated Apr 2017 | Jul 2015 | granted Dec 2015 | Apr 2017 |
| Sands Farm Quarry, Low Lanebattery storage | battery storage | 4 | application submitted may be out of dateupdated Mar 2024 | Feb 2024 | — | Mar 2024 |
| Westbury (Closed) Landfill Sitesolar farm | solar farm | 3.5 | operationalupdated Nov 2014 | Jul 2013 | granted Oct 2013 | Nov 2014 |
| Chicklade EV Service Station Solar Farmsolar farm | solar farm | 3 | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 |
| Summerslade Down Wind Clusterwind farm | wind farm | 2.2 | refusedupdated Oct 2011 | Oct 1998 | refused May 1999 | Oct 2011 |
Smaller schemes under 1 MW, mostly rooftop solar (58)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Lambdown Terrace, Swinton Barrackssolar farm | solar farm | 0.8 | approved, not builtupdated Nov 2025 | Feb 2025 | granted Aug 2025 | Nov 2025 |
| Salisbury District Hospital, Odstock Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 |
| Apetito, Canal Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Sep 2024 | Sep 2024 |
| Edinburgh Way Solar Photovolatic Panelrooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Aug 2022 | Jul 2022 | granted Sep 2022 | Aug 2022 |
| North Park, Savernakesolar farm | solar farm | 0.7 | approved, not builtupdated Dec 2025 | Apr 2025 | granted Oct 2025 | Dec 2025 |
| Herman Miller, Portal Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated May 2023 | Feb 2023 | granted Apr 2023 | May 2023 |
| Batten Road, Downtonrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2022 | Jun 2022 | granted Aug 2022 | Jul 2022 |
| Ashley Garagebattery storage | battery storage | 0.5 | application withdrawnupdated Feb 2024 | Sep 2023 | — | Feb 2024 |
| Knorr Bremse Rail Systems Uk, Westinghouse Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Apr 2026 | granted Jun 2026 | May 2026 |
| Hulse Roadrooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Apr 2022 | Jan 2022 | granted Mar 2022 | Apr 2022 |
| Stourhead, Near Meresolar farm | solar farm | 0.4 | application submittedupdated Jun 2026 | Jun 2026 | — | Jun 2026 |
| Hangar 45, Yatesbury - Extensions & Solar Panelsrooftop solar | rooftop solar | 0.4 | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 |
| Sloperton Farm, Westbrooksolar farm | solar farm | 0.3 | approved, not builtupdated Jul 2025 | Jul 2024 | granted Jun 2025 | Jul 2025 |
| Wiltshire College, Lackhamrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Apr 2023 | Jan 2023 | granted Apr 2023 | Apr 2023 |
| Chelworth Park, Chelworth Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2024 | Apr 2024 | granted Jun 2024 | Jun 2024 |
| Ratfyn Water Recycling Centre, Amesburyrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 |
| Morrisons, West Cepen Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 |
| Salisbury District Hospital, Odstock Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Dec 2025 | Jan 2026 |
| Moonraker Farm, Gastardrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Apr 2023 | granted Jun 2023 | Jul 2023 |
| Chemring Countermeasures Limited, Nettonrooftop solar | rooftop solar | 0.2 | refusedupdated Mar 2026 | Dec 2025 | refused Feb 2026 | Mar 2026 |
| Morrisons, Weymouth Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2023 | Oct 2022 | granted Dec 2022 | Jan 2023 |
| St Marys School, Curzon Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2024 | Apr 2024 | granted Jul 2024 | Sep 2024 |
| Whitewalls, Easton Greyrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — |
| HM Erlestoke Solar Arraysolar farm | solar farm | 0.2 | application submitted may be out of dateupdated Jan 2021 | Dec 2020 | — | Jan 2021 |
| The Salisbury Hospice, Salisbury District Hospitalrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Jan 2026 | granted Apr 2026 | Jun 2026 |
| Whitefields Farm, Ogbourne St Georgerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 |
| St Modwen Park, Motorwayrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2023 | Sep 2022 | granted Dec 2022 | Jan 2023 |
| St Laurence School, Ashley Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 |
| Salisbury District Hospital, Odstock Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Mar 2025 | granted May 2025 | Jun 2025 |
| Salisbury City Hallrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2022 | Dec 2021 | granted Feb 2022 | Jan 2022 |
| Washington Road, West Wilts Trading Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Sep 2024 | Oct 2024 |
| Sainsburys Superstore, Bath Roadrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — |
| Interface Business Park, Bincknoll Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Jun 2024 | granted Oct 2024 | Jan 2025 |
| Ministry Of Defence, Westwells Roadrooftop solar | rooftop solar | 0.2 | application submitted | Apr 2026 | — | — |
| Hulse Roadrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Feb 2022 | Jan 2022 | granted May 2022 | Feb 2022 |
| Wiltshire college, College Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2023 | Oct 2022 | granted Jan 2023 | Mar 2023 |
| Stowford Manor Farm, Farleigh Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Apr 2023 | granted Jul 2023 | Jul 2023 |
| Springfield Community Campus, Beechfield Road Solar Photovoltaic Arraysrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2024 | Mar 2024 | granted Apr 2024 | Jun 2024 |
| Grain Dryer, Manor Farm,rooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | May 2025 | granted Jul 2025 | Sep 2025 |
| Tesco, County Wayrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 |
| Land at Court Farmbattery storage | battery storage | — | refused on appealupdated Sep 2019 | Jan 2018 | — | Sep 2019 |
| Wick Farm, Melksham Substationbattery storage | battery storage | — | under constructionupdated May 2025 | Aug 2020 | granted Dec 2021 | May 2025 |
| Bourne Hill Council Officerooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Feb 2021 | Jan 2021 | granted Feb 2021 | Feb 2021 |
| Crudwell Road Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Apr 2021 | Mar 2021 | granted Aug 2023 | Apr 2021 |
| Southfield Farmbattery storage | battery storage | — | application withdrawnupdated Dec 2021 | Mar 2022 | — | Dec 2021 |
| Storridge Roadbattery storage | battery storage | — | approved, not builtupdated Feb 2022 | Nov 2021 | granted Oct 2023 | Feb 2022 |
| Pond Lane, Minetybattery storage | battery storage | — | approved, not builtupdated Jul 2024 | Jan 2022 | granted Feb 2024 | Jul 2024 |
| Cooles Farm, Minety Solar Park/Battery Storagebattery storage | battery storage | — | application submitted may be out of dateupdated Dec 2022 | Nov 2022 | — | Dec 2022 |
| Westbury Sewage Treatment Works, Slag Lanesolar farm | solar farm | — | approved, not builtupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 |
| Studley Farm Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not built may be out of dateupdated Dec 2022 | Sep 2021 | granted Jun 2022 | Dec 2022 |
| Solar Farm at Whistle Mead Solar Farmsolar farm | solar farm | — | application submitted may be out of dateupdated Mar 2023 | Mar 2023 | — | Mar 2023 |
| Larkhill Garrison Glover Roadsolar farm | solar farm | — | approved, not builtupdated Aug 2024 | Mar 2023 | granted Jul 2024 | Aug 2024 |
| Codford Solar Farm Phase 4battery storage | battery storage | — | approved, not builtupdated Feb 2026 | May 2023 | granted Jul 2024 | Feb 2026 |
| Chemring Countermeasures Limited, High Post Road- Solar Arrayrooftop solar | rooftop solar | — | approved, not builtupdated Jul 2024 | Jun 2023 | granted Jun 2024 | Jul 2024 |
| Codford Biogasbattery storage | battery storage | — | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 |
| Blackthorn Solar Farmbattery storage | battery storage | — | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 |
| Mod Lyneham, Calne Road Solar Array ( Project Cubit)solar farm | solar farm | — | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 |
| Mod Lyneham, Calne Road Solar Array ( Project Cubit)battery storage | battery storage | — | no application requiredupdated Sep 2025 | — | — | Sep 2025 |
9 more projects not listed (furthest or smallest).
Postcode districts in Wiltshire
| District | Projects within 10 km | Pending | Approved | Operational |
|---|---|---|---|---|
| BA12 | 7 | 1 | 2 | 1 |
| BA13 | 29 | 3 | 15 | 10 |
| BA14 | 42 | 2 | 19 | 16 |
| BA15 | 44 | 4 | 22 | 13 |
| SN4 | 44 | 1 | 26 | 14 |
| SN8 | 3 | 0 | 2 | 1 |
| SN9 | 0 | 0 | 0 | 0 |
| SN10 | 12 | 1 | 3 | 5 |
| SN11 | 20 | 4 | 9 | 5 |
| SN12 | 45 | 4 | 22 | 13 |
| SN13 | 40 | 4 | 22 | 8 |
| SN14 | 30 | 5 | 16 | 6 |
| SN15 | 34 | 5 | 19 | 8 |
| SN16 | 35 | 5 | 13 | 12 |
| SP1 | 20 | 2 | 11 | 3 |
| SP2 | 18 | 2 | 10 | 2 |
| SP3 | 8 | 1 | 2 | 3 |
| SP4 | 11 | 2 | 4 | 3 |
| SP5 | 14 | 0 | 10 | 2 |
| SP9 | 15 | 0 | 9 | 4 |
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Wiltshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.