Energy Projects Near You

Renewable energy projects in Wiltshire

167 solar, wind or battery projects of 150 kW or more are located in Wiltshire (REPD, July 2026 extract): 20 pending, 77 approved but not running, 49 operational and 8 refused. The council refused 18 of 140 decided applications (13%; UK 19%), with a median 21 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

167projects in the council area
20awaiting a decision
77approved, not running
13%of decisions refused

How Wiltshire decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Projects in Wiltshire

Projects of 1 MW and more (100)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Lime Down Solar Projectsolar farmsolar farm500application submittedupdated Jun 2026Oct 2025—Jun 2026
Lime Downbattery storagebattery storage500application submittedupdated Jun 2026Oct 2025—Jun 2026
Brockleaze, Neston Park Estatebattery storagebattery storage450application submittedupdated Aug 2025Jul 2025—Aug 2025
Norrington Gate Farm, Broughton Giffordbattery storagebattery storage150approved, not built may be out of dateupdated Jul 2022Jun 2022granted Jan 2023Jul 2022
Bradenstoke solar parksolar farmsolar farm69.8operationalupdated Jul 2024Jul 2014granted Nov 2014Jul 2024
Melksham Substation East Storagebattery storagebattery storage50operationalupdated Nov 2022May 2017granted Apr 2019Nov 2022
Stonehill Energy Storage / Lower Minetybattery storagebattery storage50operationalupdated Mar 2026Nov 2019granted Feb 2020Mar 2026
Fairholme, Minetybattery storagebattery storage50approved, not builtupdated Jul 2024Jul 2022granted May 2024Jul 2024
Stonehill Energy Storagebattery storagebattery storage50approved, not builtupdated May 2025Jul 2022granted May 2025May 2025
Stonehill Energy Storage / Upper Minetybattery storagebattery storage50operationalupdated Mar 2026Jun 2017granted Sep 2017Mar 2026
Stonehill Energy Storage / Upper Minetybattery storagebattery storage50operationalupdated Mar 2026—granted Jul 2018Mar 2026
Minety Northbattery storagebattery storage50abandonedupdated Sep 2022May 2017—Sep 2022
Minety Southbattery storagebattery storage50operationalupdated Aug 2020May 2017granted Sep 2017Aug 2020
Minety South 2battery storagebattery storage50operationalupdated Mar 2026Mar 2021granted Nov 2021Mar 2026
Ravensroost Farm, Minetybattery storagebattery storage49.9approved, not builtupdated Nov 2024Jun 2022refused Mar 2024Nov 2024
Snarlton Farmbattery storagebattery storage49.9abandonedupdated Jan 2020Mar 2019—Jan 2020
Down Barn Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated May 2023Nov 2019granted Apr 2020May 2023
National Grid Minety Substationbattery storagebattery storage49.9approved, not built may be out of dateupdated Jul 2024Aug 2020granted Jan 2021Jul 2024
Wick Farm Melksham Substationsolar farmsolar farm49.9under constructionupdated May 2025Aug 2020granted Dec 2021May 2025
Crudwell Road Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not builtupdated Feb 2026Mar 2021granted Aug 2023Feb 2026
Forest Gate Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Jun 2021Jun 2021granted Mar 2023Jun 2021
Leigh Delamere Solar farm & Battery storagesolar farmsolar farm49.9under constructionupdated Aug 2025Jun 2021granted Aug 2022Aug 2025
Studley Farm Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Jul 2022Sep 2021granted Jun 2022Jul 2022
Potterne Park Farm, Potterne Solar Farmsolar farmsolar farm49.9approved, not builtupdated May 2026Dec 2023granted Apr 2026May 2026
Snarlton Farm (Melksham solar farm)solar farmsolar farm49.6operationalupdated Feb 2017Nov 2013granted Jun 2015Feb 2017
Salisbury Substationbattery storagebattery storage49.5operationalupdated Jun 2026Aug 2019granted Dec 2021Jun 2026
Minety Substationsolar farmsolar farm40approved, not built may be out of dateupdated Jul 2022Apr 2020granted Apr 2022Jul 2022
Forest Gate Solar Farm & Battery Storagebattery storagebattery storage40approved, not built may be out of dateupdated Jun 2021Jun 2021granted Mar 2023Jun 2021
Leigh Delamere Solar farm & Battery storagebattery storagebattery storage40under constructionupdated Aug 2025Jun 2021granted Aug 2022Aug 2025
Red Barn Solar Farm & Battery Storagesolar farmsolar farm40approved, not builtupdated Feb 2026Oct 2023granted Jan 2025Feb 2026
Red Barn Solar Farm & Battery Storagebattery storagebattery storage40approved, not builtupdated Feb 2026Oct 2023granted Jan 2025Feb 2026
Blackthorn Solar Farmsolar farmsolar farm40application submittedupdated Jun 2025May 2025—Jun 2025
Water Eaton Farm / Port Farmsolar farmsolar farm34.8operationalupdated Mar 2018Apr 2014granted Aug 2014Mar 2018
Storridge Road Solar Farmsolar farmsolar farm31approved, not builtupdated Feb 2022Nov 2021granted Oct 2023Feb 2022
Beech Tree Solar Farmsolar farmsolar farm30approved, not builtupdated Aug 2025Nov 2023granted Jul 2025Aug 2025
Hoopers Pool, Southwicksolar farmsolar farm30application submittedupdated Jul 2025May 2025—Jul 2025
Whaddon Lane, Hilpertonsolar farmsolar farm25approved, not built may be out of dateupdated Sep 2023May 2021granted Apr 2022Sep 2023
Swallett Energy Parksolar farmsolar farm23approved, not builtupdated Feb 2026Dec 2023granted Jan 2026Feb 2026
Cockhill Solar Farmsolar farmsolar farm20operationalupdated Jul 2015Jun 2014granted Aug 2014Jul 2015
Tiddlywink Barn Battery Storage Power Plantbattery storagebattery storage20abandonedupdated Jun 2022Aug 2021—Jun 2022
Mopes Lane, Purton Solar Farmsolar farmsolar farm20approved, not built may be out of dateupdated Dec 2021Nov 2021granted Apr 2023Dec 2021
East Codford Solar Farm Extension Phase 3solar farmsolar farm18operationalupdated Jun 2023Apr 2019granted Dec 2020Jun 2023
Whaddon Lane, Hilpertonbattery storagebattery storage18approved, not built may be out of dateupdated Sep 2023May 2021granted Apr 2022Sep 2023
Codford Solar Farm Phase 4solar farmsolar farm18approved, not builtupdated Feb 2026May 2023granted Jul 2024Feb 2026
Stokes Marsh Farmsolar farmsolar farm16.6operationalupdated Nov 2017Aug 2013granted Dec 2013Nov 2017
Bake Farmsolar farmsolar farm16.1application withdrawnupdated Jul 2014Dec 2013—Jul 2014
Blounts Court Farm, Potternesolar farmsolar farm15refusedupdated Jul 2025Jun 2024refused May 2025Jul 2025
Lodge Farm (Poulshot)solar farmsolar farm14.5operationalupdated Apr 2015Oct 2013granted Feb 2014Apr 2015
Marsh Farmsolar farmsolar farm14operationalupdated Feb 2017Jul 2012granted Jan 2013Feb 2017
Roundponds Farm Solar Parksolar farmsolar farm13.5operationalupdated Apr 2015Jan 2014granted May 2014Apr 2015
Solar Farm at Townsend Farmsolar farmsolar farm13.5approved, not builtupdated Jan 2026Jan 2025granted Dec 2025Jan 2026
Leechpool Farm, Norrington Battery Storagebattery storagebattery storage13permission expiredupdated Aug 2020May 2018—Aug 2020
Malmesbury Road Solar Farmsolar farmsolar farm13approved, not builtupdated Mar 2022Sep 2021granted Oct 2023Mar 2022
Boscombe Airfieldsolar farmsolar farm12.3operationalupdated Apr 2015Jun 2014granted Nov 2014Apr 2015
Castle Combe Circuitsolar farmsolar farm12operationalupdated Apr 2015Jul 2014granted Nov 2014Apr 2015
Little Chalfield Solar Farmsolar farmsolar farm12refused on appealupdated May 2015May 2014refused Sep 2014May 2015
Spittleborough Farmsolar farmsolar farm12operationalupdated Aug 2014Jul 2013granted Dec 2013Aug 2014
Bentham House Farm, Mopes Lane Solar Farmsolar farmsolar farm12approved, not builtupdated Feb 2026Sep 2024granted Jun 2025Feb 2026
Battens Farm Solar Parksolar farmsolar farm11operationalupdated May 2014May 2013granted Aug 2013May 2014
Norrington Common Solar Farmsolar farmsolar farm10operationalupdated Feb 2017Nov 2012granted Apr 2013Feb 2017
Minety Substationbattery storagebattery storage10approved, not built may be out of dateupdated Jul 2022Apr 2020granted Apr 2022Jul 2022
Park Farmbattery storagebattery storage10permission expiredupdated Apr 2021Mar 2018granted May 2018Apr 2021
Solar Farm at East of Battens Farmsolar farmsolar farm10approved, not builtupdated Jan 2026Oct 2024granted Sep 2025Jan 2026
High Penn Solar Parksolar farmsolar farm9.6operationalupdated Sep 2014Feb 2013granted Oct 2013Sep 2014
Marsh Farm Hilpertonsolar farmsolar farm9.1operationalupdated Sep 2018Jan 2014granted Apr 2014Sep 2018
Braydon Manor Farmsolar farmsolar farm8.7operationalupdated Jul 2016Jun 2013granted Oct 2013Jul 2016
Mill Farm, Teffontbattery storagebattery storage8.5approved, not builtupdated Apr 2024Oct 2023granted Mar 2024Apr 2024
Bentham Farmsolar farmsolar farm8operationalupdated Jul 2015Oct 2013granted Dec 2014Jul 2015
Cooles Farm, Minety Solar Park/Battery Storagesolar farmsolar farm8application submitted may be out of dateupdated Dec 2022Nov 2022—Dec 2022
Deptford Farm solar parksolar farmsolar farm7.8refusedupdated Mar 2014May 2013refused Dec 2013Mar 2014
Rodbourne Rail Farm Solar Parksolar farmsolar farm7.6operationalupdated Mar 2014May 2012granted Nov 2012Mar 2014
Newnton Dairy Farmsolar farmsolar farm7.2operationalupdated Apr 2014Jun 2013granted Sep 2013Apr 2014
Rudge Farm Solar Farmsolar farmsolar farm7operationalupdated May 2016Jul 2012granted Dec 2012May 2016
Hullavington Solar Parksolar farmsolar farm7operationalupdated May 2016May 2013granted Nov 2013May 2016
Land at East Farmsolar farmsolar farm6.8operationalupdated Jun 2014Jan 2013granted Mar 2013Jun 2014
Land at Poles Hole Farmsolar farmsolar farm6.8operationalupdated Jul 2018May 2015granted Oct 2015Jul 2018
Somerford Farm, Brinkworthbattery storagebattery storage6.6approved, not builtupdated Oct 2024Apr 2022granted Oct 2024Oct 2024
Manor Farm (Wiltshire)solar farmsolar farm6.3operationalupdated Mar 2017Mar 2014granted Dec 2014Mar 2017
Blenches Millsolar farmsolar farm6.1operationalupdated Jul 2018Nov 2012granted Nov 2013Jul 2018
Land at East Farm - extensionsolar farmsolar farm6operationalupdated Jul 2016Oct 2013granted Jan 2014Jul 2016
East Farm (Clay Pit Hill) - Extension IIsolar farmsolar farm6application withdrawnupdated Dec 2018Apr 2018—Dec 2018
Sands Farm Quarry, Low Lanesolar farmsolar farm6application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024
Malmesbury Solarsolar farmsolar farm5operationalupdated Mar 2013Mar 2011granted May 2011Mar 2013
Kingston Farmsolar farmsolar farm5operationalupdated Mar 2013Mar 2011granted May 2011Mar 2013
Lake Farmsolar farmsolar farm5operationalupdated Mar 2013Jan 2011granted Apr 2011Mar 2013
Wickfield Farmsolar farmsolar farm5operationalupdated Jul 2017Mar 2014granted Jun 2014Jul 2017
Rock Farm / Goldborough Farm (Rookwood)solar farmsolar farm5operationalupdated Mar 2015Dec 2013granted Jul 2014Mar 2015
Bake Farm Solar Farmsolar farmsolar farm5operationalupdated Jun 2017Nov 2014granted Mar 2015Jun 2017
Trowle Commonsolar farmsolar farm5operationalupdated Apr 2016Jan 2015granted Jun 2015Apr 2016
Land West Side of Axe and Cleaver Lanesolar farmsolar farm5operationalupdated May 2016May 2015granted Aug 2015May 2016
Park Grounds Farmsolar farmsolar farm5abandonedupdated Apr 2017Aug 2015granted Dec 2015Apr 2017
Lower End Farmsolar farmsolar farm4.9operationalupdated Aug 2017Mar 2014granted Aug 2014Aug 2017
Brook Hall Farmsolar farmsolar farm4.7operationalupdated May 2016Jun 2015granted Nov 2015May 2016
Land At Moor Lane Farmsolar farmsolar farm4.5refusedupdated Sep 2016Aug 2015refused Aug 2016Sep 2016
Bollands Hillsolarsolar4refused on appealupdated Oct 2015Apr 2014refused Sep 2014Oct 2015
Land north of Ashton Roadsolar farmsolar farm4operationalupdated Apr 2017Jul 2015granted Dec 2015Apr 2017
Sands Farm Quarry, Low Lanebattery storagebattery storage4application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024
Westbury (Closed) Landfill Sitesolar farmsolar farm3.5operationalupdated Nov 2014Jul 2013granted Oct 2013Nov 2014
Chicklade EV Service Station Solar Farmsolar farmsolar farm3application submittedupdated Mar 2026Feb 2026—Mar 2026
Summerslade Down Wind Clusterwind farmwind farm2.2refusedupdated Oct 2011Oct 1998refused May 1999Oct 2011
Smaller schemes under 1 MW, mostly rooftop solar (58)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Lambdown Terrace, Swinton Barrackssolar farmsolar farm0.8approved, not builtupdated Nov 2025Feb 2025granted Aug 2025Nov 2025
Salisbury District Hospital, Odstock Roadrooftop solarrooftop solar0.8approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024
Apetito, Canal Roadrooftop solarrooftop solar0.7approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024
Edinburgh Way Solar Photovolatic Panelrooftop solarrooftop solar0.7approved, not built may be out of dateupdated Aug 2022Jul 2022granted Sep 2022Aug 2022
North Park, Savernakesolar farmsolar farm0.7approved, not builtupdated Dec 2025Apr 2025granted Oct 2025Dec 2025
Herman Miller, Portal Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023
Batten Road, Downtonrooftop solarrooftop solar0.5approved, not builtupdated Jul 2022Jun 2022granted Aug 2022Jul 2022
Ashley Garagebattery storagebattery storage0.5application withdrawnupdated Feb 2024Sep 2023—Feb 2024
Knorr Bremse Rail Systems Uk, Westinghouse Wayrooftop solarrooftop solar0.4approved, not builtupdated May 2026Apr 2026granted Jun 2026May 2026
Hulse Roadrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Apr 2022Jan 2022granted Mar 2022Apr 2022
Stourhead, Near Meresolar farmsolar farm0.4application submittedupdated Jun 2026Jun 2026—Jun 2026
Hangar 45, Yatesbury - Extensions & Solar Panelsrooftop solarrooftop solar0.4application submittedupdated Mar 2026Feb 2026—Mar 2026
Sloperton Farm, Westbrooksolar farmsolar farm0.3approved, not builtupdated Jul 2025Jul 2024granted Jun 2025Jul 2025
Wiltshire College, Lackhamrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2023Jan 2023granted Apr 2023Apr 2023
Chelworth Park, Chelworth Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2024Apr 2024granted Jun 2024Jun 2024
Ratfyn Water Recycling Centre, Amesburyrooftop solarrooftop solar0.3approved, not builtupdated Oct 2022Aug 2022granted Oct 2022Oct 2022
Morrisons, West Cepen Wayrooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024
Salisbury District Hospital, Odstock Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Sep 2025granted Dec 2025Jan 2026
Moonraker Farm, Gastardrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023Apr 2023granted Jun 2023Jul 2023
Chemring Countermeasures Limited, Nettonrooftop solarrooftop solar0.2refusedupdated Mar 2026Dec 2025refused Feb 2026Mar 2026
Morrisons, Weymouth Streetrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Oct 2022granted Dec 2022Jan 2023
St Marys School, Curzon Streetrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Apr 2024granted Jul 2024Sep 2024
Whitewalls, Easton Greyrooftop solarrooftop solar0.2application submittedJun 2026——
HM Erlestoke Solar Arraysolar farmsolar farm0.2application submitted may be out of dateupdated Jan 2021Dec 2020—Jan 2021
The Salisbury Hospice, Salisbury District Hospitalrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Jan 2026granted Apr 2026Jun 2026
Whitefields Farm, Ogbourne St Georgerooftop solarrooftop solar0.2approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024
St Modwen Park, Motorwayrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jan 2023Sep 2022granted Dec 2022Jan 2023
St Laurence School, Ashley Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025
Salisbury District Hospital, Odstock Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025
Salisbury City Hallrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jan 2022Dec 2021granted Feb 2022Jan 2022
Washington Road, West Wilts Trading Estaterooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024
Sainsburys Superstore, Bath Roadrooftop solarrooftop solar0.2application submittedJun 2026——
Interface Business Park, Bincknoll Lanerooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Jun 2024granted Oct 2024Jan 2025
Ministry Of Defence, Westwells Roadrooftop solarrooftop solar0.2application submittedApr 2026——
Hulse Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Feb 2022Jan 2022granted May 2022Feb 2022
Wiltshire college, College Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Oct 2022granted Jan 2023Mar 2023
Stowford Manor Farm, Farleigh Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023Apr 2023granted Jul 2023Jul 2023
Springfield Community Campus, Beechfield Road Solar Photovoltaic Arraysrooftop solarrooftop solar0.2approved, not builtupdated Jun 2024Mar 2024granted Apr 2024Jun 2024
Grain Dryer, Manor Farm,rooftop solarrooftop solar0.2approved, not builtupdated Sep 2025May 2025granted Jul 2025Sep 2025
Tesco, County Wayrooftop solarrooftop solar0.1approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026
Land at Court Farmbattery storagebattery storage—refused on appealupdated Sep 2019Jan 2018—Sep 2019
Wick Farm, Melksham Substationbattery storagebattery storage—under constructionupdated May 2025Aug 2020granted Dec 2021May 2025
Bourne Hill Council Officerooftop solarrooftop solar—approved, not built may be out of dateupdated Feb 2021Jan 2021granted Feb 2021Feb 2021
Crudwell Road Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Apr 2021Mar 2021granted Aug 2023Apr 2021
Southfield Farmbattery storagebattery storage—application withdrawnupdated Dec 2021Mar 2022—Dec 2021
Storridge Roadbattery storagebattery storage—approved, not builtupdated Feb 2022Nov 2021granted Oct 2023Feb 2022
Pond Lane, Minetybattery storagebattery storage—approved, not builtupdated Jul 2024Jan 2022granted Feb 2024Jul 2024
Cooles Farm, Minety Solar Park/Battery Storagebattery storagebattery storage—application submitted may be out of dateupdated Dec 2022Nov 2022—Dec 2022
Westbury Sewage Treatment Works, Slag Lanesolar farmsolar farm—approved, not builtupdated Nov 2022Aug 2022granted Oct 2022Nov 2022
Studley Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Dec 2022Sep 2021granted Jun 2022Dec 2022
Solar Farm at Whistle Mead Solar Farmsolar farmsolar farm—application submitted may be out of dateupdated Mar 2023Mar 2023—Mar 2023
Larkhill Garrison Glover Roadsolar farmsolar farm—approved, not builtupdated Aug 2024Mar 2023granted Jul 2024Aug 2024
Codford Solar Farm Phase 4battery storagebattery storage—approved, not builtupdated Feb 2026May 2023granted Jul 2024Feb 2026
Chemring Countermeasures Limited, High Post Road- Solar Arrayrooftop solarrooftop solar—approved, not builtupdated Jul 2024Jun 2023granted Jun 2024Jul 2024
Codford Biogasbattery storagebattery storage—approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023
Blackthorn Solar Farmbattery storagebattery storage—application submittedupdated Jun 2025May 2025—Jun 2025
Mod Lyneham, Calne Road Solar Array ( Project Cubit)solar farmsolar farm—application submittedupdated Sep 2025Jul 2025—Sep 2025
Mod Lyneham, Calne Road Solar Array ( Project Cubit)battery storagebattery storage—no application requiredupdated Sep 2025——Sep 2025

9 more projects not listed (furthest or smallest).

Postcode districts in Wiltshire

DistrictProjects within 10 kmPendingApprovedOperational
BA127121
BA132931510
BA144221916
BA154442213
SN44412614
SN83021
SN90000
SN1012135
SN1120495
SN124542213
SN13404228
SN14305166
SN15345198
SN163551312
SP1202113
SP2182102
SP38123
SP411243
SP5140102
SP915094

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Wiltshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.