Energy Projects Near You

Sands Farm Quarry, Low Lane (6 MW solar farm)

Sands Farm Quarry, Low Lane is a 6 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 28 February 2024, no decision recorded; the record was last updated on 18 March 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
application submittedmay be out of datestatus in REPD
18 March 2024record last updated
Wiltshirecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
28 February 2024Application submitted

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
application submitted
Record last updated
18 March 2024
Operator or applicant
Valencia Waster Management Limited
Planning authority
Wiltshire
Planning application reference
PL/2024/01599
Site area
7.6 ha
Address (REPD)
Sands Farm Quarry, Low Lane, Calne
Council area (by location)
Wiltshire
Name in REPD
Sands Farm Quarry, Low Lane - Solar Panels
REPD reference
16057

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
High Penn Solar Parksolar farm9.6operational1.2
Forest Gate Solar Farm & Battery Storagesolar farm49.9approved, not built6.7
Bradenstoke solar parksolar farm69.8operational7.3
Swallett Energy Parksolar farm23approved, not built9.4
Lake Farmsolar farm5operational10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.441, -1.9795).