Energy Projects Near You

Forest Gate Solar Farm & Battery Storage (49.9 MW)

Forest Gate Solar Farm & Battery Storage is a 49.9 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 March 2023, not yet built; the record was last updated on 28 June 2021. REPD records the planning permission as expiring on 10 March 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
28 June 2021record last updated
Wiltshirecouncil area

REPD records the planning permission as expiring on 10 March 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started.

Planning timeline

DateStage
11 June 2021Application submitted
10 March 2023Planning permission granted
10 March 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
28 June 2021
Operator or applicant
Eden Renewables
Planning authority
Wiltshire
Planning application reference
PL/2021/06112
Site area
82.3 ha
Address (REPD)
Forest Gate, Pewsham, Chippenham
Council area (by location)
Wiltshire
Time to decision
91 weeks
Contracts for Difference
AR6
Name in REPD
Forest Gate - Solar Farm & Battery Storage
REPD reference
9229

The scheme also includes 40 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wick Farm Melksham Substationsolar farm49.9under construction5.9
Lake Farmsolar farm5operational6.2
High Penn Solar Parksolar farm9.6operational6.4
Sands Farm Quarry, Low Lanesolar farm6application submitted6.7
Melksham Substation East Storagebattery storage50operational7.2
Red Barn Solar Farm & Battery Storagesolar farm40approved, not built7.3
Snarlton Farmbattery storage49.9abandoned7.4
Battens Farm Solar Parksolar farm11operational7.5
Snarlton Farm (Melksham solar farm)solar farm49.6operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4429, -2.0768).