Energy Projects Near You

Battens Farm Solar Park (11 MW)

Battens Farm Solar Park is an 11 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2014; the record was last updated on 20 May 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWsolar farm
operationalstatus in REPD
20 May 2014record last updated
Wiltshirecouncil area

Planning timeline

DateStage
10 May 2013Application submitted
8 August 2013Planning permission granted
15 March 2014Operational

Project details

Technology
solar farm
Capacity
11 MW
Status (REPD)
operational
Record last updated
20 May 2014
Operator or applicant
Battens Farm Solar Park Ltd
Planning authority
Wiltshire
Planning application reference
13/01311/FUL
Address (REPD)
Battens Farm, Allington, Chippenham, Wiltshire
Council area (by location)
Wiltshire
Time to decision
13 weeks
REPD reference
1476

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tiddlywink Barn Battery Storage Power Plantbattery storage20abandoned1.4
Solar Farm at East of Battens Farmsolar farm10approved, not built1.4
Leigh Delamere Solar farm & Battery storagesolar farm49.9under construction3.0
Red Barn Solar Farm & Battery Storagesolar farm40approved, not built3.4
Castle Combe Circuitsolar farm12operational3.9
Lake Farmsolar farm5operational5.4
Hullavington Solar Parksolar farm7operational6.8
Forest Gate Solar Farm & Battery Storagesolar farm49.9approved, not built7.5
Brockleaze, Neston Park Estatebattery storage450application submitted8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.482, -2.165).