Solar Farm at East of Battens Farm (10 MW)

Solar Farm at East of Battens Farm is a 10 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 September 2025, not yet built; the record was last updated on 26 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtstatus in REPD
26 January 2026record last updated
Wiltshirecouncil area

Planning timeline

DateStage
29 October 2024Application submitted
26 September 2025Planning permission granted
26 September 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
26 January 2026
Operator or applicant
Noventum Power Limited
Planning authority
Wiltshire
Planning application reference
PL/2024/09410
Site area
16.1 ha
Address (REPD)
East of Battens Farm, Allington
Council area (by location)
Wiltshire
Time to decision
47 weeks
Name in REPD
North Allington Solar Farm - Solar Farm
REPD reference
17531

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tiddlywink Barn Battery Storage Power Plantbattery storage20abandoned<0.1
Battens Farm Solar Parksolar farm11operational1.4
Castle Combe Circuitsolar farm12operational2.6
Leigh Delamere Solar farm & Battery storagesolar farm49.9under construction3.3
Red Barn Solar Farm & Battery Storagesolar farm40approved, not built4.7
Lake Farmsolar farm5operational6.8
Hullavington Solar Parksolar farm7operational7.1
Brockleaze, Neston Park Estatebattery storage450application submitted7.8
Manor Farm (Wiltshire)solar farm6.3operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4809, -2.1855).