Brockleaze, Neston Park Estate (450 MW battery storage)

Brockleaze, Neston Park Estate is a 450 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 9 July 2025, no decision recorded; the record was last updated on 22 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

450 MWbattery storage
application submittedstatus in REPD
22 August 2025record last updated
Wiltshirecouncil area

Planning timeline

DateStage
9 July 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
450 MW
Status (REPD)
application submitted
Record last updated
22 August 2025
Operator or applicant
Grenergy Renewables UK Limited
Planning authority
Wiltshire
Planning application reference
PL/2025/05552
Address (REPD)
Neston Park Estate, Corsham
Council area (by location)
Wiltshire
Name in REPD
Brockleaze, Neston Park Estate - Battery Energy Storage
REPD reference
18670

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Melksham Substation East Storagebattery storage50operational2.4
Manor Farm (Wiltshire)solar farm6.3operational2.5
Studley Farm Solar Farm & Battery Storagesolar farm49.9approved, not built2.9
Norrington Common Solar Farmsolar farm10operational3.2
Wick Farm Melksham Substationsolar farm49.9under construction3.2
Leechpool Farm, Norrington Battery Storagebattery storage13permission expired3.5
Roundponds Farm Solar Parksolar farm13.5operational3.7
Norrington Gate Farm, Broughton Giffordbattery storage150approved, not built4.0
Little Chalfield Solar Farmsolar farm12refused on appeal4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4105, -2.1833).