Energy Projects Near You

Wick Farm Melksham Substation (49.9 MW solar farm)

Wick Farm Melksham Substation is a 49.9 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction; the record was last updated on 6 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
under constructionstatus in REPD
6 May 2025record last updated
Wiltshirecouncil area

Planning timeline

DateStage
19 August 2020Application submitted
17 December 2021Planning permission granted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
6 May 2025
Operator or applicant
JBM Solar Projects
Planning authority
Wiltshire
Planning application reference
20/06840/FUL
Site area
96.3 ha
Address (REPD)
Land North of Melksham Substat, Near Melksham, Chippenham,
Council area (by location)
Wiltshire
Time to decision
69 weeks
Contracts for Difference
AR4
REPD reference
8062

Recorded together with Wick Farm, Melksham Substation (battery storage, under construction).

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Melksham Substation East Storagebattery storage50operational1.3
Brockleaze, Neston Park Estatebattery storage450application submitted3.2
Roundponds Farm Solar Parksolar farm13.5operational3.4
Norrington Common Solar Farmsolar farm10operational3.4
Leechpool Farm, Norrington Battery Storagebattery storage13permission expired3.4
Norrington Gate Farm, Broughton Giffordbattery storage150approved, not built4.1
Snarlton Farmbattery storage49.9abandoned4.1
Studley Farm Solar Farm & Battery Storagesolar farm49.9approved, not built4.3
Snarlton Farm (Melksham solar farm)solar farm49.6operational5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4062, -2.1383).