Snarlton Farm (Melksham solar farm) (49.6 MW)

Snarlton Farm (Melksham solar farm) is a 49.6 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 1 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.6 MWsolar farm
operationalstatus in REPD
1 February 2017record last updated
Wiltshirecouncil area

Planning timeline

DateStage
19 November 2013Application submitted
16 April 2014Refused by the planning authority
3 July 2014Appeal lodged
18 June 2015Planning permission granted
18 June 2015Appeal allowed
23 November 2015Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
49.6 MW
Status (REPD)
operational
Record last updated
1 February 2017
Operator or applicant
Foresight
Planning authority
Wiltshire
Planning application reference
13/06140/FUL
Appeal reference
APP/Y3940/A/14/2221012
Site area
80.5 ha
Address (REPD)
Land at Snarlton Farm Snarlton Lane Melksham Wilts
Council area (by location)
Wiltshire
Time to decision
82 weeks
REPD reference
1335

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Snarlton Farmbattery storage49.9abandoned0.9
Wick Farm Melksham Substationsolar farm49.9under construction5.0
Roundponds Farm Solar Parksolar farm13.5operational5.1
Melksham Substation East Storagebattery storage50operational5.3
Leechpool Farm, Norrington Battery Storagebattery storage13permission expired5.4
Solar Farm at Townsend Farmsolar farm13.5approved, not built5.5
Norrington Gate Farm, Broughton Giffordbattery storage150approved, not built5.7
Norrington Common Solar Farmsolar farm10operational5.7
Studley Farm Solar Farm & Battery Storagesolar farm49.9approved, not built7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3734, -2.0897).