Energy Projects Near You

Norrington Gate Farm, Broughton Gifford (150 MW battery storage)

Norrington Gate Farm, Broughton Gifford is a 150 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 January 2023, not yet built; the record was last updated on 8 July 2022. REPD also records that the planning permission expired on 6 January 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

150 MWbattery storage
approved, not builtmay be out of datestatus in REPD
8 July 2022record last updated
Wiltshirecouncil area

REPD also records that the planning permission expired on 6 January 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
13 June 2022Application submitted
6 January 2023Planning permission granted
6 January 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
150 MW
Status (REPD)
approved, not built
Record last updated
8 July 2022
Operator or applicant
ADV 003 Limited
Planning authority
Wiltshire
Planning application reference
PL/2022/03914
Address (REPD)
Norrington Gate Farm, Norrington Gate, Broughton Gifford, Melksham
Council area (by location)
Wiltshire
Time to decision
30 weeks
Name in REPD
Norrington Gate Farm, Broughton Gifford - Battery Energy Storage Facility
REPD reference
11612

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Leechpool Farm, Norrington Battery Storagebattery storage13permission expired0.7
Roundponds Farm Solar Parksolar farm13.5operational0.8
Norrington Common Solar Farmsolar farm10operational0.9
Studley Farm Solar Farm & Battery Storagesolar farm49.9approved, not built1.6
Melksham Substation East Storagebattery storage50operational2.9
Whaddon Lane, Hilpertonsolar farm25approved, not built3.2
Little Chalfield Solar Farmsolar farm12refused on appeal3.3
Marsh Farm Hilpertonsolar farm9.1operational3.8
Brockleaze, Neston Park Estatebattery storage450application submitted4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3756, -2.1711).