Energy Projects Near You

Studley Farm Solar Farm & Battery Storage (49.9 MW)

Studley Farm Solar Farm & Battery Storage is a 49.9 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 June 2022, not yet built; the record was last updated on 8 July 2022. REPD records the planning permission as expiring on 9 June 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
8 July 2022record last updated
Wiltshirecouncil area

REPD records the planning permission as expiring on 9 June 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
30 September 2021Application submitted
9 June 2022Planning permission granted
9 June 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
8 July 2022
Operator or applicant
Melksham Calne Green Limited
Planning authority
Wiltshire
Planning application reference
PL/2021/08690
Site area
35.6 ha
Address (REPD)
Studley Farm, Atworth, Melksham
Council area (by location)
Wiltshire
Time to decision
36 weeks
Contracts for Difference
AR5
Name in REPD
Studley Farm - Solar Farm & Battery Storage
REPD reference
11620

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Norrington Common Solar Farmsolar farm10operational1.3
Norrington Gate Farm, Broughton Giffordbattery storage150approved, not built1.6
Leechpool Farm, Norrington Battery Storagebattery storage13permission expired1.7
Roundponds Farm Solar Parksolar farm13.5operational1.9
Little Chalfield Solar Farmsolar farm12refused on appeal2.1
Brockleaze, Neston Park Estatebattery storage450application submitted2.9
Melksham Substation East Storagebattery storage50operational2.9
Manor Farm (Wiltshire)solar farm6.3operational3.5
Whaddon Lane, Hilpertonsolar farm25approved, not built4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3846, -2.1892).