Energy Projects Near You

Roundponds Farm Solar Park (13.5 MW)

Roundponds Farm Solar Park is a 13.5 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 15 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.5 MWsolar farm
operationalstatus in REPD
15 April 2015record last updated
Wiltshirecouncil area

Planning timeline

DateStage
9 January 2014Application submitted
23 May 2014Planning permission granted
15 December 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
13.5 MW
Status (REPD)
operational
Record last updated
15 April 2015
Operator or applicant
Hive Energy
Planning authority
Wiltshire
Planning application reference
13/06707/FUL
Site area
30.6 ha
Address (REPD)
Land South East Of Leechpool Farm Norrington Lane Broughton Gifford Wiltshire
Council area (by location)
Wiltshire
Time to decision
19 weeks
REPD reference
2023

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Leechpool Farm, Norrington Battery Storagebattery storage13permission expired0.2
Norrington Common Solar Farmsolar farm10operational0.6
Norrington Gate Farm, Broughton Giffordbattery storage150approved, not built0.8
Studley Farm Solar Farm & Battery Storagesolar farm49.9approved, not built1.9
Melksham Substation East Storagebattery storage50operational2.2
Wick Farm Melksham Substationsolar farm49.9under construction3.4
Brockleaze, Neston Park Estatebattery storage450application submitted3.7
Little Chalfield Solar Farmsolar farm12refused on appeal3.9
Whaddon Lane, Hilpertonsolar farm25approved, not built3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3801, -2.1627).