Energy Projects Near You

Melksham Substation East Storage (50 MW)

Melksham Substation East Storage is a 50 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 November 2022; the record was last updated on 22 November 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
operationalstatus in REPD
22 November 2022record last updated
Wiltshirecouncil area

Planning timeline

DateStage
10 May 2017Application submitted
26 April 2019Planning permission granted
1 January 2022Construction started
7 November 2022Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
operational
Record last updated
22 November 2022
Operator or applicant
Statera Energy / Melksham East Storage
Planning authority
Wiltshire
Planning application reference
17/04110/FUL
Address (REPD)
Land to the south of Melksham Substation Westlands Farm Westlands Lane Whitley Melksham
Council area (by location)
Wiltshire
Time to decision
102 weeks
REPD reference
6953

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wick Farm Melksham Substationsolar farm49.9under construction1.3
Norrington Common Solar Farmsolar farm10operational2.1
Leechpool Farm, Norrington Battery Storagebattery storage13permission expired2.2
Roundponds Farm Solar Parksolar farm13.5operational2.2
Brockleaze, Neston Park Estatebattery storage450application submitted2.4
Norrington Gate Farm, Broughton Giffordbattery storage150approved, not built2.9
Studley Farm Solar Farm & Battery Storagesolar farm49.9approved, not built2.9
Snarlton Farmbattery storage49.9abandoned4.4
Manor Farm (Wiltshire)solar farm6.3operational4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3992, -2.1539).