Energy Projects Near You

Manor Farm (Wiltshire) (6.3 MW solar farm)

Manor Farm (Wiltshire) is a 6.3 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2015; the record was last updated on 16 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.3 MWsolar farm
operationalstatus in REPD
16 March 2017record last updated
Wiltshirecouncil area

Planning timeline

DateStage
17 March 2014Application submitted
23 December 2014Planning permission granted
1 March 2015Construction started
1 August 2015Operational

Project details

Technology
solar farm
Capacity
6.3 MW
Status (REPD)
operational
Record last updated
16 March 2017
Operator or applicant
RB & T Barton Ltd
Planning authority
Wiltshire
Planning application reference
14/03084/FUL
Site area
14.2 ha
Address (REPD)
Land East of Manor Farm, Wadswick Box, Corsham
Council area (by location)
Wiltshire
Time to decision
40 weeks
REPD reference
1923

Earlier applications for this site

ApplicationMWSubmittedOutcome
Manor Farm (Wiltshire) 13/04055/FUL9.620 September 2013refused 18 December 2013

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brockleaze, Neston Park Estatebattery storage450application submitted2.5
Little Chalfield Solar Farmsolar farm12refused on appeal3.3
Studley Farm Solar Farm & Battery Storagesolar farm49.9approved, not built3.5
Norrington Common Solar Farmsolar farm10operational4.5
Melksham Substation East Storagebattery storage50operational4.7
Leechpool Farm, Norrington Battery Storagebattery storage13permission expired4.9
Norrington Gate Farm, Broughton Giffordbattery storage150approved, not built5.0
Roundponds Farm Solar Parksolar farm13.5operational5.1
Wick Farm Melksham Substationsolar farm49.9under construction5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4095, -2.2189).