Little Chalfield Solar Farm (12 MW)

Little Chalfield Solar Farm is a 12 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 18 May 2015; the record was last updated on 27 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
refused on appealstatus in REPD
27 May 2015record last updated
Wiltshirecouncil area

Planning timeline

DateStage
29 May 2014Application submitted
29 September 2014Refused by the planning authority
9 December 2014Appeal lodged
18 May 2015Appeal refused

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
refused on appeal
Record last updated
27 May 2015
Operator or applicant
Solar Planning
Planning authority
Wiltshire
Planning application reference
14/05253/FUL
Appeal reference
APP/Y3940/A/14/2228679
Site area
24.7 ha
Address (REPD)
Land West Of Ganbrook Farm Little Chalfield Wiltshire
Council area (by location)
Wiltshire
Time to decision
18 weeks
REPD reference
2031

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Studley Farm Solar Farm & Battery Storagesolar farm49.9approved, not built2.1
Manor Farm (Wiltshire)solar farm6.3operational3.3
Norrington Gate Farm, Broughton Giffordbattery storage150approved, not built3.3
Norrington Common Solar Farmsolar farm10operational3.4
Leechpool Farm, Norrington Battery Storagebattery storage13permission expired3.6
Roundponds Farm Solar Parksolar farm13.5operational3.9
Kingston Farmsolar farm5operational4.1
Brockleaze, Neston Park Estatebattery storage450application submitted4.2
Whaddon Lane, Hilpertonsolar farm25approved, not built4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3801, -2.2185).