Energy Projects Near You

Solar, wind and battery projects near Calne (SN11)

20 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SN11 (Wiltshire): 4 are waiting for a planning decision, 9 approved but not yet running, 5 operational. The largest live scheme is Forest Gate Solar Farm & Battery Storage (49.9 MW solar farm, approved on 10 March 2023, not yet built; REPD status may be out of date), 5.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20projects within 10 km
4awaiting a decision
9approved, not running
5operational

Projects within 10 km of SN11

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sands Farm Quarry, Low Lanesolar farmsolar farm6application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Wiltshire1.4
Sands Farm Quarry, Low Lanebattery storagebattery storage4application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Wiltshire1.4
High Penn Solar Parksolar farmsolar farm9.6operationalupdated Sep 2014Feb 2013granted Oct 2013Sep 2014Wiltshire1.6
Forest Gate Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Jun 2021Jun 2021granted Mar 2023Jun 2021Wiltshire5.4
Forest Gate Solar Farm & Battery Storagebattery storagebattery storage40approved, not built may be out of dateupdated Jun 2021Jun 2021granted Mar 2023Jun 2021Wiltshire5.4
Bradenstoke solar parksolar farmsolar farm69.8operationalupdated Jul 2024Jul 2014granted Nov 2014Jul 2024Wiltshire7.7
Hopton Road Industrial Estatesolar farmsolar farm1.3operationalupdated Sep 2014Jul 2013granted Aug 2013Sep 2014Wiltshire7.9
Parsonage Wayrooftop solarrooftop solar1.6approved, not built may be out of dateupdated Nov 2022Jul 2022granted Oct 2022Nov 2022Wiltshire8.2
Lake Farmsolar farmsolar farm5operationalupdated Mar 2013Jan 2011granted Apr 2011Mar 2013Wiltshire9.1
Swallett Energy Parksolar farmsolar farm23approved, not builtupdated Feb 2026Dec 2023granted Jan 2026Feb 2026Wiltshire9.2
Snarlton Farm (Melksham solar farm)solar farmsolar farm49.6operationalupdated Feb 2017Nov 2013granted Jun 2015Feb 2017Wiltshire9.7
Snarlton Farmbattery storagebattery storage49.9abandonedupdated Jan 2020Mar 2019—Jan 2020Wiltshire9.8
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
St Marys School, Curzon Streetrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Apr 2024granted Jul 2024Sep 2024Wiltshire0.6
Hangar 45, Yatesbury - Extensions & Solar Panelsrooftop solarrooftop solar0.4application submittedupdated Mar 2026Feb 2026—Mar 2026Wiltshire5.6
Sloperton Farm, Westbrooksolar farmsolar farm0.3approved, not builtupdated Jul 2025Jul 2024granted Jun 2025Jul 2025Wiltshire6.6
Mod Lyneham, Calne Road Solar Array ( Project Cubit)solar farmsolar farm—application submittedupdated Sep 2025Jul 2025—Sep 2025Wiltshire7.8
Mod Lyneham, Calne Road Solar Array ( Project Cubit)battery storagebattery storage—no application requiredupdated Sep 2025——Sep 2025Wiltshire7.8
Wiltshire College, Lackhamrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2023Jan 2023granted Apr 2023Apr 2023Wiltshire7.9
Grain Dryer, Manor Farm,rooftop solarrooftop solar0.2approved, not builtupdated Sep 2025May 2025granted Jul 2025Sep 2025Wiltshire9.9
Morrisons, West Cepen Wayrooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Wiltshire9.9

Distance from the average position of the SN11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm10235079.2
Rooftop solar615003
Battery storage4110044

MW in pipeline: pending, approved and under-construction capacity.

How Wiltshire decides solar, wind and battery applications

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

All projects in Wiltshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SN11, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.