Energy Projects Near You

High Penn Solar Park (9.6 MW)

High Penn Solar Park is a 9.6 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2014; the record was last updated on 2 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.6 MWsolar farm
operationalstatus in REPD
2 September 2014record last updated
Wiltshirecouncil area

Planning timeline

DateStage
25 February 2013Application submitted
8 October 2013Planning permission granted
30 March 2014Operational

Project details

Technology
solar farm
Capacity
9.6 MW
Status (REPD)
operational
Record last updated
2 September 2014
Operator or applicant
Hive Energy
Planning authority
Wiltshire
Planning application reference
12/04169/FUL
Site area
32.3 ha
Address (REPD)
High Penn Farm, Calne, Wiltshire
Council area (by location)
Wiltshire
Time to decision
32 weeks
REPD reference
1998

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sands Farm Quarry, Low Lanesolar farm6application submitted1.2
Bradenstoke solar parksolar farm69.8operational6.3
Forest Gate Solar Farm & Battery Storagesolar farm49.9approved, not built6.4
Swallett Energy Parksolar farm23approved, not built8.2
Lake Farmsolar farm5operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4512, -1.986).