Energy Projects Near You

Solar, wind and battery projects near Devizes (SN10)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SN10 (Wiltshire): 1 is waiting for a planning decision, 3 approved but not yet running, 5 operational. The largest live scheme is Potterne Park Farm, Potterne Solar Farm (49.9 MW solar farm, approved on 20 April 2026, not yet built), 3.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
1awaiting a decision
3approved, not running
5operational

Projects within 10 km of SN10

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Blounts Court Farm, Potternesolar farmsolar farm15refusedupdated Jul 2025Jun 2024refused May 2025Jul 2025Wiltshire2.0
Potterne Park Farm, Potterne Solar Farmsolar farmsolar farm49.9approved, not builtupdated May 2026Dec 2023granted Apr 2026May 2026Wiltshire3.2
Hopton Road Industrial Estatesolar farmsolar farm1.3operationalupdated Sep 2014Jul 2013granted Aug 2013Sep 2014Wiltshire4.0
Solar Farm at Townsend Farmsolar farmsolar farm13.5approved, not builtupdated Jan 2026Jan 2025granted Dec 2025Jan 2026Wiltshire4.7
Lower End Farmsolar farmsolar farm4.9operationalupdated Aug 2017Mar 2014granted Aug 2014Aug 2017Wiltshire4.9
Stokes Marsh Farmsolar farmsolar farm16.6operationalupdated Nov 2017Aug 2013granted Dec 2013Nov 2017Wiltshire7.5
Bollands Hillsolarsolar4refused on appealupdated Oct 2015Apr 2014refused Sep 2014Oct 2015Wiltshire7.8
Craysmarsh Solar Farmsolar farmsolar farm1.8operationalupdated Mar 2013Mar 2012granted Jun 2012Mar 2013Wiltshire8.0
Snarlton Farm (Melksham solar farm)solar farmsolar farm49.6operationalupdated Feb 2017Nov 2013granted Jun 2015Feb 2017Wiltshire8.2
Snarlton Farmbattery storagebattery storage49.9abandonedupdated Jan 2020Mar 2019—Jan 2020Wiltshire9.1
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
HM Erlestoke Solar Arraysolar farmsolar farm0.2application submitted may be out of dateupdated Jan 2021Dec 2020—Jan 2021Wiltshire7.0
Sloperton Farm, Westbrooksolar farmsolar farm0.3approved, not builtupdated Jul 2025Jul 2024granted Jun 2025Jul 2025Wiltshire7.9

Distance from the average position of the SN10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm10135164
Solar100010
Battery storage100000

MW in pipeline: pending, approved and under-construction capacity.

How Wiltshire decides solar, wind and battery applications

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

All projects in Wiltshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SN10, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.