Potterne Park Farm, Potterne Solar Farm (49.9 MW)

Potterne Park Farm, Potterne Solar Farm is a 49.9 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 April 2026, not yet built; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
19 May 2026record last updated
Wiltshirecouncil area

Planning timeline

DateStage
20 December 2023Application submitted
3 July 2025Refused by the planning authority
20 April 2026Planning permission granted
20 April 2026Appeal allowed
20 April 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
19 May 2026
Operator or applicant
Potterne Solar Project Limited
Planning authority
Wiltshire
Planning application reference
PL/2023/10332
Site area
79.8 ha
Address (REPD)
S/O Potterne Park Farm, Nr Potterne, Devizes
Council area (by location)
Wiltshire
Time to decision
122 weeks
Name in REPD
Potterne Park Farm, Potterne - Solar Farm
REPD reference
15715

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blounts Court Farm, Potternesolar farm15refused2.2
Solar Farm at Townsend Farmsolar farm13.5approved, not built5.2
Stokes Marsh Farmsolar farm16.6operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3087, -1.9868).