Blounts Court Farm, Potterne (15 MW solar farm)

Blounts Court Farm, Potterne is a 15 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 30 May 2025; the record was last updated on 8 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
refusedstatus in REPD
8 July 2025record last updated
Wiltshirecouncil area

Planning timeline

DateStage
11 June 2024Application submitted
30 May 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
refused
Record last updated
8 July 2025
Operator or applicant
Greenfield Energy Developments Limited
Planning authority
Wiltshire
Planning application reference
PL/2024/04926
Site area
28.4 ha
Address (REPD)
E/O Blounts Court Farm, Potterne, Devizes
Council area (by location)
Wiltshire
Time to decision
50 weeks
Name in REPD
Blounts Court Farm, Potterne - Solar Panels
REPD reference
14529

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Potterne Park Farm, Potterne Solar Farmsolar farm49.9approved, not built2.2
Solar Farm at Townsend Farmsolar farm13.5approved, not built3.3
Stokes Marsh Farmsolar farm16.6operational5.7
Snarlton Farm (Melksham solar farm)solar farm49.6operational7.9
Snarlton Farmbattery storage49.9abandoned8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3245, -2.0068).