Energy Projects Near You

Leigh Delamere Solar farm & Battery storage (49.9 MW)

Leigh Delamere Solar farm & Battery storage is a 49.9 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 14 July 2025; the record was last updated on 5 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
under constructionstatus in REPD
5 August 2025record last updated
Wiltshirecouncil area

Planning timeline

DateStage
14 June 2021Application submitted
11 August 2022Planning permission granted
14 July 2025Construction started

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
5 August 2025
Operator or applicant
Eden Renewables
Planning authority
Wiltshire
Planning application reference
PL/2021/06100
Site area
87.9 ha
Address (REPD)
The S/O The M4 At Leigh Delamere, To The W/O Leigh, Delamere Motorway Services, Chippenham
Council area (by location)
Wiltshire
Time to decision
60 weeks
Contracts for Difference
AR6
Name in REPD
Leigh Delamere - Solar farm & Battery storage
REPD reference
9237

The scheme also includes 40 MW of battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Battens Farm Solar Parksolar farm11operational3.0
Tiddlywink Barn Battery Storage Power Plantbattery storage20abandoned3.3
Solar Farm at East of Battens Farmsolar farm10approved, not built3.3
Red Barn Solar Farm & Battery Storagesolar farm40approved, not built3.3
Castle Combe Circuitsolar farm12operational3.6
Hullavington Solar Parksolar farm7operational3.8
Lake Farmsolar farm5operational5.7
Lime Down Solar Projectsolar farm500application submitted6.1
Lime Downbattery storage500application submitted6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5088, -2.1716).