Minety South (50 MW battery storage)

Minety South is a 50 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2022; the record was last updated on 21 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
operationalstatus in REPD
21 August 2020record last updated
Wiltshirecouncil area

Planning timeline

DateStage
5 May 2017Application submitted
28 September 2017Planning permission granted
1 October 2022Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
operational
Record last updated
21 August 2020
Operator or applicant
Statera Energy
Planning authority
Wiltshire
Planning application reference
17/03941/FUL
Address (REPD)
Land South of Minety Substation Minety
Council area (by location)
Wiltshire
Time to decision
21 weeks
Name in REPD
Minety South - Battery Storage
REPD reference
7184

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Minety Northbattery storage50abandoned<0.1
National Grid Minety Substationbattery storage49.9approved, not built1.0
Minety South 2battery storage50operational1.0
Stonehill Energy Storage / Upper Minetybattery storage50operational1.2
Stonehill Energy Storage / Upper Minetybattery storage50operational1.2
Stonehill Energy Storage / Lower Minetybattery storage50operational1.2
Fairholme, Minetybattery storage50approved, not built1.2
Minety Substationsolar farm40approved, not built1.3
Stonehill Energy Storagebattery storage50approved, not built1.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6015, -1.9882).