Energy Projects Near You

Stonehill Energy Storage / Upper Minety (50 MW, 2017 application)

Stonehill Energy Storage / Upper Minety is a 50 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2020; the record was last updated on 9 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
operationalstatus in REPD
9 March 2026record last updated
Wiltshirecouncil area

Planning timeline

DateStage
29 June 2017Application submitted
21 September 2017Planning permission granted
1 December 2019Construction started
1 December 2020Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
operational
Record last updated
9 March 2026
Operator or applicant
Penso Power (BW ESS)
Planning authority
Wiltshire
Planning application reference
17/05526/FUL
Address (REPD)
Land Adjacent To Electricity S, Stonehill, Charlton, Malmesbury,
Council area (by location)
Wiltshire
Time to decision
12 weeks
REPD reference
20399

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stonehill Energy Storage / Upper Minetybattery storage50operational<0.1
Stonehill Energy Storage / Lower Minetybattery storage50operational<0.1
Stonehill Energy Storagebattery storage50approved, not built0.2
National Grid Minety Substationbattery storage49.9approved, not built0.4
Minety Substationsolar farm40approved, not built0.5
Minety South 2battery storage50operational0.5
Minety Southbattery storage50operational1.2
Minety Northbattery storage50abandoned1.2
Fairholme, Minetybattery storage50approved, not built1.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6053, -2.004).