Stonehill Energy Storage (50 MW)

Stonehill Energy Storage is a 50 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 May 2025, not yet built; the record was last updated on 20 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
20 May 2025record last updated
Wiltshirecouncil area

Planning timeline

DateStage
20 July 2022Application submitted
24 June 2024Refused by the planning authority
2 May 2025Planning permission granted
2 May 2025Appeal allowed
2 May 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
20 May 2025
Operator or applicant
Penso Power (BW ESS)
Planning authority
Wiltshire
Planning application reference
PL/2022/05504
Appeal reference
AP-37312
Address (REPD)
Stonehill, Minety
Council area (by location)
Wiltshire
Time to decision
145 weeks
REPD reference
11812

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stonehill Energy Storage / Lower Minetybattery storage50operational0.2
Stonehill Energy Storage / Upper Minetybattery storage50operational0.2
Stonehill Energy Storage / Upper Minetybattery storage50operational0.2
National Grid Minety Substationbattery storage49.9approved, not built0.5
Minety Substationsolar farm40approved, not built0.5
Minety South 2battery storage50operational0.6
Minety Northbattery storage50abandoned1.4
Minety Southbattery storage50operational1.4
Fairholme, Minetybattery storage50approved, not built2.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6063, -2.0062).