National Grid Minety Substation (49.9 MW battery storage)
National Grid Minety Substation is a 49.9 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 January 2021, not yet built; the record was last updated on 9 July 2024. REPD also records that the planning permission expired on 25 January 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.
REPD also records that the planning permission expired on 25 January 2024, so the project may not go ahead in this form.
Planning timeline
| Date | Stage |
|---|---|
| 28 August 2020 | Application submitted |
| 25 January 2021 | Planning permission granted |
| 25 January 2024 | Permission expired |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 49.9 MW
- Status (REPD)
- approved, not built
- Record last updated
- 9 July 2024
- Operator or applicant
- Harbour Energy
- Planning authority
- Wiltshire
- Planning application reference
- 20/07390/FUL
- Address (REPD)
- National Grid Minety Substatio, Stonehill, Charlton, Malmesbury, Wiltshire
- Council area (by location)
- Wiltshire
- Time to decision
- 21 weeks
- REPD reference
- 8021
Who decides
| Applications | Wiltshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 140 | 10,236 |
| Refused | 18 (13%) | 19% |
| Solar refused | 13 of 110 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 4 of 29 | 16% |
| Median time from submission to decision | 20.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 7 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Minety South 2 | battery storage | 50 | operational | 0.2 |
| Stonehill Energy Storage / Lower Minety | battery storage | 50 | operational | 0.4 |
| Stonehill Energy Storage / Upper Minety | battery storage | 50 | operational | 0.4 |
| Stonehill Energy Storage / Upper Minety | battery storage | 50 | operational | 0.4 |
| Stonehill Energy Storage | battery storage | 50 | approved, not built | 0.5 |
| Minety Substation | solar farm | 40 | approved, not built | 0.8 |
| Minety South | battery storage | 50 | operational | 1.0 |
| Minety North | battery storage | 50 | abandoned | 1.0 |
| Fairholme, Minety | battery storage | 50 | approved, not built | 1.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6068, -1.999).