Energy Projects Near You

National Grid Minety Substation (49.9 MW battery storage)

National Grid Minety Substation is a 49.9 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 January 2021, not yet built; the record was last updated on 9 July 2024. REPD also records that the planning permission expired on 25 January 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
9 July 2024record last updated
Wiltshirecouncil area

REPD also records that the planning permission expired on 25 January 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
28 August 2020Application submitted
25 January 2021Planning permission granted
25 January 2024Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
9 July 2024
Operator or applicant
Harbour Energy
Planning authority
Wiltshire
Planning application reference
20/07390/FUL
Address (REPD)
National Grid Minety Substatio, Stonehill, Charlton, Malmesbury, Wiltshire
Council area (by location)
Wiltshire
Time to decision
21 weeks
REPD reference
8021

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Minety South 2battery storage50operational0.2
Stonehill Energy Storage / Lower Minetybattery storage50operational0.4
Stonehill Energy Storage / Upper Minetybattery storage50operational0.4
Stonehill Energy Storage / Upper Minetybattery storage50operational0.4
Stonehill Energy Storagebattery storage50approved, not built0.5
Minety Substationsolar farm40approved, not built0.8
Minety Southbattery storage50operational1.0
Minety Northbattery storage50abandoned1.0
Fairholme, Minetybattery storage50approved, not built1.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6068, -1.999).