Minety South 2 (50 MW battery storage)

Minety South 2 is a 50 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 November 2022; the record was last updated on 9 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
operationalstatus in REPD
9 March 2026record last updated
Wiltshirecouncil area

Planning timeline

DateStage
22 March 2021Application submitted
8 November 2021Planning permission granted
7 November 2022Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
operational
Record last updated
9 March 2026
Operator or applicant
Statera Energy
Planning authority
Wiltshire
Planning application reference
PL/2021/04151
Address (REPD)
Purlieus Farm, Minety, Malmesbury
Council area (by location)
Wiltshire
Time to decision
33 weeks
Name in REPD
Minety South 2 - Battery Storage Facility
REPD reference
9063

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
National Grid Minety Substationbattery storage49.9approved, not built0.2
Stonehill Energy Storage / Upper Minetybattery storage50operational0.5
Stonehill Energy Storage / Upper Minetybattery storage50operational0.5
Stonehill Energy Storage / Lower Minetybattery storage50operational0.5
Stonehill Energy Storagebattery storage50approved, not built0.6
Minety Northbattery storage50abandoned1.0
Minety Southbattery storage50operational1.0
Minety Substationsolar farm40approved, not built1.0
Fairholme, Minetybattery storage50approved, not built1.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.608, -1.9977).