Deptford Farm solar park (7.8 MW)

Deptford Farm solar park is a 7.8 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 10 December 2013; the record was last updated on 7 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.8 MWsolar farm
refusedstatus in REPD
7 March 2014record last updated
Wiltshirecouncil area

Planning timeline

DateStage
24 May 2013Application submitted
10 December 2013Refused by the planning authority

Project details

Technology
solar farm
Capacity
7.8 MW
Status (REPD)
refused
Record last updated
7 March 2014
Operator or applicant
Brilliant Harvest Installations
Planning authority
Wiltshire
Planning application reference
13/00699/FUL
Site area
11.0 ha
Address (REPD)
Land north of Deptford Farm Wylye Warminster Wiltshire
Council area (by location)
Wiltshire
Time to decision
29 weeks
REPD reference
1680

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at East Farm - extensionsolar farm6operational3.0
East Codford Solar Farm Extension Phase 3solar farm18operational3.0
Land at East Farmsolar farm6.8operational3.7
East Farm (Clay Pit Hill) - Extension IIsolar farm6application withdrawn4.2
Codford Solar Farm Phase 4solar farm18approved, not built4.3
Mill Farm, Teffontbattery storage8.5approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.161, -1.975).