Mill Farm, Teffont (8.5 MW battery storage)
Mill Farm, Teffont is an 8.5 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 March 2024, not yet built; the record was last updated on 26 April 2024.
8.5 MWbattery storage
approved, not builtstatus in REPD
26 April 2024record last updated
Wiltshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 27 October 2023 | Application submitted |
| 12 March 2024 | Planning permission granted |
| 12 March 2036 | Permission due to expire (unless work starts) |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 8.5 MW
- Status (REPD)
- approved, not built
- Record last updated
- 26 April 2024
- Operator or applicant
- Private Energy Partners Pty Limited
- Planning authority
- Wiltshire
- Planning application reference
- PL/2023/08472
- Address (REPD)
- Electricity Sub Station 73m From Goldens 9m From Unnamed Road, Road To Mill Farm, Teffont, Salisbury
- Council area (by location)
- Wiltshire
- Time to decision
- 20 weeks
- Name in REPD
- Mill Farm, Teffont - Battery Energy Storage
- REPD reference
- 15320
Who decides
| Applications | Wiltshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 140 | 10,236 |
| Refused | 18 (13%) | 19% |
| Solar refused | 13 of 110 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 4 of 29 | 16% |
| Median time from submission to decision | 20.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 7 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| East Farm (Clay Pit Hill) - Extension II | solar farm | 6 | application withdrawn | 9.1 |
| Deptford Farm solar park | solar farm | 7.8 | refused | 9.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0781, -2.0033).