Energy Projects Near You

Mill Farm, Teffont (8.5 MW battery storage)

Mill Farm, Teffont is an 8.5 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 March 2024, not yet built; the record was last updated on 26 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.5 MWbattery storage
approved, not builtstatus in REPD
26 April 2024record last updated
Wiltshirecouncil area

Planning timeline

DateStage
27 October 2023Application submitted
12 March 2024Planning permission granted
12 March 2036Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
8.5 MW
Status (REPD)
approved, not built
Record last updated
26 April 2024
Operator or applicant
Private Energy Partners Pty Limited
Planning authority
Wiltshire
Planning application reference
PL/2023/08472
Address (REPD)
Electricity Sub Station 73m From Goldens 9m From Unnamed Road, Road To Mill Farm, Teffont, Salisbury
Council area (by location)
Wiltshire
Time to decision
20 weeks
Name in REPD
Mill Farm, Teffont - Battery Energy Storage
REPD reference
15320

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Farm (Clay Pit Hill) - Extension IIsolar farm6application withdrawn9.1
Deptford Farm solar parksolar farm7.8refused9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0781, -2.0033).