Energy Projects Near You

Solar, wind and battery projects near Salisbury (SP3)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SP3 (Wiltshire): 1 is waiting for a planning decision, 2 approved but not yet running, 3 operational. The largest live scheme is Mill Farm, Teffont (8.5 MW battery storage, approved on 12 March 2024, not yet built), 2.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
1awaiting a decision
2approved, not running
3operational

Projects within 10 km of SP3

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mill Farm, Teffontbattery storagebattery storage8.5approved, not builtupdated Apr 2024Oct 2023granted Mar 2024Apr 2024Wiltshire2.8
East Farm (Clay Pit Hill) - Extension IIsolar farmsolar farm6application withdrawnupdated Dec 2018Apr 2018—Dec 2018Wiltshire6.3
Deptford Farm solar parksolar farmsolar farm7.8refusedupdated Mar 2014May 2013refused Dec 2013Mar 2014Wiltshire7.1
Chicklade EV Service Station Solar Farmsolar farmsolar farm3application submittedupdated Mar 2026Feb 2026—Mar 2026Wiltshire8.1
Land at East Farm - extensionsolar farmsolar farm6operationalupdated Jul 2016Oct 2013granted Jan 2014Jul 2016Wiltshire8.1
Land at East Farmsolar farmsolar farm6.8operationalupdated Jun 2014Jan 2013granted Mar 2013Jun 2014Wiltshire8.4
East Codford Solar Farm Extension Phase 3solar farmsolar farm18operationalupdated Jun 2023Apr 2019granted Dec 2020Jun 2023Wiltshire8.5
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Codford Biogasbattery storagebattery storage—approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Wiltshire7.8

Distance from the average position of the SP3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm610313
Battery storage202008.5

MW in pipeline: pending, approved and under-construction capacity.

How Wiltshire decides solar, wind and battery applications

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

All projects in Wiltshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.