Land at East Farm (6.8 MW solar farm)

Land at East Farm is a 6.8 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 9 November 2013; the record was last updated on 2 June 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.8 MWsolar farm
operationalstatus in REPD
2 June 2014record last updated
Wiltshirecouncil area

Planning timeline

DateStage
3 January 2013Application submitted
19 March 2013Planning permission granted
9 October 2013Construction started
9 November 2013Operational

Project details

Technology
solar farm
Capacity
6.8 MW
Status (REPD)
operational
Record last updated
2 June 2014
Operator or applicant
Anesco
Planning authority
Wiltshire
Planning application reference
W/12/02216/FUL
Address (REPD)
Codford Dairy, East Farm, Church Lane, Codford
Council area (by location)
Wiltshire
Time to decision
11 weeks
REPD reference
1748

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at East Farm - extensionsolar farm6operational0.7
East Codford Solar Farm Extension Phase 3solar farm18operational0.8
Codford Solar Farm Phase 4solar farm18approved, not built1.8
East Farm (Clay Pit Hill) - Extension IIsolar farm6application withdrawn2.6
Deptford Farm solar parksolar farm7.8refused3.7