Codford Solar Farm Phase 4 (18 MW)

Codford Solar Farm Phase 4 is an 18 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 July 2024, not yet built; the record was last updated on 24 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWsolar farm
approved, not builtstatus in REPD
24 February 2026record last updated
Wiltshirecouncil area

Planning timeline

DateStage
19 May 2023Application submitted
17 July 2024Planning permission granted
17 July 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
18 MW
Status (REPD)
approved, not built
Record last updated
24 February 2026
Operator or applicant
JM Stratton & Company
Planning authority
Wiltshire
Planning application reference
PL/2023/03024
Site area
28.5 ha
Address (REPD)
East Farm, Codford St Mary, Warminster
Council area (by location)
Wiltshire
Time to decision
61 weeks
REPD reference
14045

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Codford Solar Farm Extension Phase 3solar farm18operational1.6
Land at East Farmsolar farm6.8operational1.8
Land at East Farm - extensionsolar farm6operational2.1
Deptford Farm solar parksolar farm7.8refused4.3
East Farm (Clay Pit Hill) - Extension IIsolar farm6application withdrawn4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1935, -2.0097).