Energy Projects Near You

East Codford Solar Farm Extension Phase 3 (18 MW)

East Codford Solar Farm Extension Phase 3 is an 18 MW solar farm project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 2022; the record was last updated on 13 June 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWsolar farm
operationalstatus in REPD
13 June 2023record last updated
Wiltshirecouncil area

Planning timeline

DateStage
8 April 2019Application submitted
18 December 2020Planning permission granted
25 April 2022Construction started
1 September 2022Operational

Project details

Technology
solar farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
13 June 2023
Operator or applicant
Centrica Plc
Planning authority
Wiltshire
Planning application reference
19/03576/FUL
Site area
17.8 ha
Address (REPD)
Clay Pit Hill Codford Down Eas, Codford, Warminster
Council area (by location)
Wiltshire
Time to decision
89 weeks
REPD reference
7405

Who decides

ApplicationsWiltshireUK
Decided applications (solar, wind, battery)14010,236
Refused18 (13%)19%
Solar refused13 of 11012%
Onshore wind refused1 of 145%
Battery storage refused4 of 2916%
Median time from submission to decision20.9 weeks17.0 weeks
Appeals lodged / allowed5 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at East Farm - extensionsolar farm6operational0.5
Land at East Farmsolar farm6.8operational0.8
Codford Solar Farm Phase 4solar farm18approved, not built1.6
Deptford Farm solar parksolar farm7.8refused3.0
East Farm (Clay Pit Hill) - Extension IIsolar farm6application withdrawn3.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1788, -2.0079).