Solar, wind and battery projects near Salisbury (SP5)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SP5 (Wiltshire): 10 approved but not yet running, 2 operational. The largest live scheme is Beech Tree Solar Farm (30 MW solar farm, approved on 30 July 2025, not yet built), 5.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SP5
Projects of 1 MW and more (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sewage Works, Southampton Road Solar Farmsolar farm | solar farm | 2 | application withdrawnupdated Jul 2024 | Aug 2023 | — | Jul 2024 | Wiltshire | 4.2 |
| Bake Farmsolar farm | solar farm | 16.1 | application withdrawnupdated Jul 2014 | Dec 2013 | — | Jul 2014 | Wiltshire | 5.3 |
| Bake Farm Solar Farmsolar farm | solar farm | 5 | operationalupdated Jun 2017 | Nov 2014 | granted Mar 2015 | Jun 2017 | Wiltshire | 5.3 |
| Beech Tree Solar Farmsolar farm | solar farm | 30 | approved, not builtupdated Aug 2025 | Nov 2023 | granted Jul 2025 | Aug 2025 | Wiltshire | 5.4 |
| Salisbury Substationbattery storage | battery storage | 49.5 | operationalupdated Jun 2026 | Aug 2019 | granted Dec 2021 | Jun 2026 | Wiltshire | 8.8 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Salisbury District Hospital, Odstock Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Dec 2025 | Jan 2026 | Wiltshire | 2.8 |
| The Salisbury Hospice, Salisbury District Hospitalrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Jan 2026 | granted Apr 2026 | Jun 2026 | Wiltshire | 2.8 |
| Salisbury District Hospital, Odstock Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Wiltshire | 2.8 |
| Salisbury District Hospital, Odstock Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Mar 2025 | granted May 2025 | Jun 2025 | Wiltshire | 2.8 |
| Batten Road, Downtonrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2022 | Jun 2022 | granted Aug 2022 | Jul 2022 | Wiltshire | 3.1 |
| Salisbury City Hallrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2022 | Dec 2021 | granted Feb 2022 | Jan 2022 | Wiltshire | 5.8 |
| Bourne Hill Council Officerooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Feb 2021 | Jan 2021 | granted Feb 2021 | Feb 2021 | Wiltshire | 5.8 |
| Hulse Roadrooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Apr 2022 | Jan 2022 | granted Mar 2022 | Apr 2022 | Wiltshire | 6.7 |
| Hulse Roadrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Feb 2022 | Jan 2022 | granted May 2022 | Feb 2022 | Wiltshire | 6.7 |
Distance from the average position of the SP5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 0 | 1 | 1 | 0 | 30 |
| Rooftop solar | 9 | 0 | 9 | 0 | 0 | 2.7 |
| Battery storage | 1 | 0 | 0 | 1 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Wiltshire decides solar, wind and battery applications
| Applications | Wiltshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 140 | 10,236 |
| Refused | 18 (13%) | 19% |
| Solar refused | 13 of 110 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 4 of 29 | 16% |
| Median time from submission to decision | 20.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 7 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SP5, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.